Practitioner · Course 2: RFQ and Supplier Quotation Comparison · Lesson 5 of 5

Building a complete quotation comparison sheet for a new order

Level: PractitionerTime: 45 minutesOrder used: A (the T-shirt) and B (the jeans), as separate worked examplesTool: Quotation comparison sheet
This lesson is for anyone who must build a full RFQ-to-decision comparison from a blank page for a new order, drawing on every step from lessons 2.1 to 2.4. Money figures are teaching examples in US dollars.
BuyerNorthline Apparel (overseas clothing brand)
FactoryDelta Garments (garment factory)
ProductsT-shirt (Order A) and jeans (Order B), two separate comparisons
Quantities15,000 pieces (A) and 3,000 pieces (B)
MethodRFQ, read, normalise, weigh risk, decide
DocumentComplete quotation comparison sheet
02Opening

This page teaches how to build one complete quotation comparison, from writing the RFQ to recommending a supplier, for anyone doing this for a new order for the first time

Lessons 2.1 to 2.4 each taught one part of this process: writing a fair RFQ, reading what a quotation actually states, normalising quotations onto one basis, and weighing a normalised price against lead-time and quality risk. This lesson puts all four parts together in order, on two new worked examples: a repeat of Order A's T-shirt and, for contrast, Order B's jeans, whose only fixed figure is its total FOB target of USD 9.80. This lesson mainly teaches the decision flow: carrying a comparison from a blank RFQ through to one supported recommendation.

03Before you start

What you need, and what this lesson does not cover

You need: all four prior lessons of this course: writing an RFQ (2.1), reading a quotation (2.2), normalising quotations (2.3), and weighing risk (2.4).

By the end of this lesson you can:

  • carry a comparison through all four steps of this course, in order, for a new order;
  • assemble one comparison sheet that records the RFQ facts, each quotation's readings, the normalised prices, and the weighed risk;
  • write a one-line recommendation that states which supplier and why;
  • adapt the same four-step method to an order whose costing breakdown is not yet fully fixed, such as Order B (jeans).

Not covered here: what happens once a purchase order is placed with the chosen supplier, taught in the next course.

04Key terms

Words you will meet in this lesson

TermMeaning
Comparison sheetThe single working document that records an RFQ's facts, each supplier's quotation, the normalised prices, and the estimated risk, ending in one recommendation.
Recommendation lineThe one sentence at the end of a comparison sheet stating which supplier is chosen and the main reason.
Sourcing decisionThe final choice of which supplier to place an order with, made after price, terms and risk have all been weighed.
Repeat orderA new order for a style the buyer has already produced before, often with the same or a similar supplier.
Fixed FOB targetA total price the buyer states it is aiming for, used as a benchmark even before a full cost breakdown is agreed, as with Order B (jeans)'s USD 9.80.
Audit trailThe record, kept on the comparison sheet itself, of what each supplier quoted and why one was chosen, so the decision can be reviewed later.
05Teaching
The rule

A complete quotation comparison carries one order through four steps in order, RFQ, read, normalise, weigh risk, and ends in one recorded recommendation

Each of the four prior lessons taught one link in this chain, and none of the four is a substitute for the others: a well-written RFQ does not by itself normalise the quotes that come back, and a normalised price does not by itself account for a supplier's lead-time or quality record. A complete comparison sheet keeps a record of all four steps for one order, from the six RFQ facts through to the one line stating which supplier was chosen and why, so that the decision can be checked or repeated later.

Order A repeat, four steps recorded: RFQ sent to 2 factories, 2 quotations read, prices normalised to 3.20 and 3.13, risk-weighted result 3.20 effectively cheaper once Factory Y's delay risk is counted
What you meet in real life

How much of the sheet is filled in, and how fast, varies by whether the order is new or a repeat, and by how firm the cost figures already are

What can differThe shapes you will meetWhy it matters to you
New order versus repeat orderA repeat of Order A can reuse an existing supplier record for the risk-weighing step, as lesson 2.4 showed. A genuinely new style has no supplier history to weigh yet, so risk is assessed from qualification information instead (T13-C01).A repeat order's comparison can move faster through step four; a new order needs more care there since no track record exists.
How firm the underlying cost figures areOrder A's own costing is fully fixed, fabric, trims, making, overhead and profit each stated (in the earlier fixed-cost breakdown lesson in Track 12). Order B (jeans)'s own costing breakdown is not yet fully fixed; only its total FOB target of USD 9.80 is fixed.A comparison can still be built around a fixed total target even without every cost component broken out, as long as every supplier is asked to quote against the same target and the same six RFQ facts.
Export MTO order versus a hybrid sourcing patternAn export MTO order like Order A is a one-time confirmed quantity. An agent like Meridian Sourcing, or a factory serving both export and domestic buyers, may run the same four-step comparison for a hybrid mix of one-time and repeat orders across several buyers.The four steps do not change with the business model; what changes is how often the sheet is rebuilt versus reused for a repeat order from the same buyer.
Who signs off the recommendationA merchandiser may recommend a supplier that a manager or owner still approves before the purchase order is placed. An agent's recommendation goes to the buyer it represents for the buyer's own final approval.The comparison sheet's audit trail matters most at this point, since whoever approves the choice needs to see the same four steps the recommender used, not just the final number.
The case we follow

Delta Garments' own merchandising team builds one complete comparison sheet for Order B's jeans, alongside the completed Order A example

Delta Garments already has Order A's comparison complete, from lessons 2.1 to 2.4. Its merchandising team now builds a second, parallel comparison for a new inquiry on Order B's jeans, where only the FOB target of USD 9.80 is fixed.

StepOrder A (complete example)Order B (jeans) (new comparison)
1. RFQSix facts fixed and sent to 2 factories (2.1)Six facts fixed, including target FOB of 9.80, sent to 2 factories
2. ReadQuantity, inclusions, exclusions, validity checked (2.2)Quantity (3,000 pieces), inclusions and validity checked the same way
3. NormalisePrices normalised to 3.20 and 3.13 (2.3)Both quotations normalised to FOB terms and 3,000-piece quantity
4. Weigh riskFactory Y's delay risk estimated at 0.15/piece (2.4)Each candidate factory's own on-time delivery record checked
The worked number

Order B (jeans)'s comparison uses the same four-step arithmetic as Order A, even though its own cost breakdown is not yet fully fixed

Order B (jeans) quantity: 3,000 pieces
Two candidate factories quote FOB 9.80 and FOB 9.95 respectively, both against the same fixed target and six RFQ facts
Normalised gap (both already FOB, same quantity, same payment terms; no normalising adjustment needed): 9.95 - 9.80 = 0.15 USD per piece
If the 9.80 factory's own on-time delivery record is 100% and the 9.95 factory's is also 100%, risk-weighing changes nothing here, and the 9.80 factory is recommended on price alone: total order value 3,000 x 9.80 = 29,400 USD
Order B (jeans), two quotations against one fixed FOB targetFactory 1: FOB 9.80, 100% on-timeFactory 2: FOB 9.95, 100% on-time
The same four-step method applies whether or not every cost component is broken out. Order B (jeans)'s comparison uses only its fixed FOB target and the same RFQ, read, normalise, weigh-risk steps as Order A.
The method

Build a complete quotation comparison sheet in five steps

  1. Write one RFQ stating all six facts from lesson 2.1, and send the identical document to every candidate supplier.
  2. Read each returned quotation for its quantity, inclusions, exclusions and validity period, from lesson 2.2.
  3. Normalise every quotation onto one common basis, from lesson 2.3.
  4. Weigh each normalised price against the supplier's own on-time delivery and quality fault record, from lesson 2.4.
  5. Record one recommendation line stating which supplier is chosen and the main reason, so the decision has an audit trail.
The trap

A common mistake is skipping straight from the RFQ to a recommendation, treating the normalising and risk-weighing steps as optional extra work on a routine repeat order

A merchandiser handling a repeat order under time pressure often assumes a familiar supplier's price can simply be compared against a new quote's headline number, skipping the reading, normalising and risk-weighing steps this course teaches because "it's the same order as before." A repeat order still needs its own comparison built fresh, since a supplier's price, its stated terms, and its own on-time delivery record can all have moved since the last time the same style was ordered. Skipping steps to save time on a routine order risks exactly the wrong-supplier outcome lessons 2.2 to 2.4 each showed a cost for.

Old price assumed unchangedComparison rebuilt fresh"Same order as before" skipsreading, normalising andrisk-weighing steps.All four steps rerun; a movedprice or record is caughtbefore the order is placed.
A repeat order is still a new comparison. A supplier's price and record can move between orders even for a familiar style.
06In plain words

Choosing a supplier well means doing four things in order, every time: ask for a price with every fact stated clearly, read what actually comes back closely, adjust the numbers so they are really comparable, and weigh in how reliable each supplier has actually been across its past orders. Writing all four steps down on one sheet, ending in one sentence saying which supplier was chosen and why, means the decision can be checked or explained later, not just remembered.

07Quick check
  • A complete comparison carries one order through RFQ, read, normalise, and weigh risk, in that order.
  • A repeat order still needs its own fresh comparison; prices and records can change since the last time.
  • A comparison can still be built around a fixed total target even when not every cost component is broken out, as with Order B (jeans).
  • The four-step method does not change between export MTO orders and a hybrid mix of order types.
  • Recording the recommendation line, with its reason, gives the decision an audit trail for later review.
  • Skipping the reading, normalising or risk-weighing step to save time risks the exact costs the earlier lessons in this course showed.
08Workplace scenario

Delta Garments' merchandising team is asked to recommend a jeans supplier for Order B within one hour, based only on the two headline FOB prices

A manager, needing a fast answer, asks the merchandising team to recommend a supplier for Order B (jeans) within the hour, using only the two prices already received: FOB 9.80 and FOB 9.95.

Here is what the team has been given so far:

Order B (jeans) inquiry, two quotations received. Factory 1: FOB 9.80. Factory 2: FOB 9.95. Quantity, inclusions, validity and on-time delivery records: not yet checked.

Can the team give a fully supported recommendation within the hour on the two prices alone? Decide before opening the answer.

Show decision

Not a fully supported one, no. Two facts decide this.

First, the two prices have not yet been read for quantity, inclusions, exclusions or validity, so it is not yet known whether 9.80 and 9.95 are quoted on the same basis at all; one could exclude an item the other includes.

Second, neither factory's on-time delivery or quality fault record has been checked yet, so even if the prices are confirmed comparable, a hidden risk difference could still change the recommendation, as it did for Factory Y in lesson 2.4.

The team can report the two headline prices as a preliminary figure within the hour, but should state clearly that the recommendation is provisional until the reading, normalising and risk-weighing steps are completed, likely within a day once both factories confirm the missing details.

09What it costs

A recommendation given without completing all four steps risks a decision that has to be reopened once the missing facts surface

Framed qualitatively, a provisional recommendation treated as final, if it later turns out the cheaper factory excluded a cost item or carries a weaker on-time record, forces the same decision to be reopened after some commitment, fabric booking, or supplier notification, has already been made on the incomplete comparison.

Order B (jeans)'s total order value at the lower quoted price: 3,000 x 9.80 = 29,400 USD, a decision worth reopening carefully rather than finalising within one hour on price alone
10Working template

Quotation comparison sheet: the complete four-tab workbook carries one order from RFQ facts to a recorded recommendation

Open the Quotation comparison sheet workbook linked below. Its four tabs, "RFQ facts," "Quote reading," "Normalise," and "Weigh risk," match the four lessons of this course in order, ending in a "Recommendation" row on the last tab. Fill in the yellow "Your order" columns across all four tabs for your own new order, in order, before writing your own recommendation line.

[Download the Quotation comparison sheet](../../templates/T13-C02-quotation-comparison-sheet.xlsx)

Download the Quotation comparison sheet (Excel)

11Check yourself

1. What are the four steps, in order, of a complete quotation comparison?

2. Order B (jeans)'s own cost breakdown is not fully fixed, only its FOB target of USD 9.80. Can a complete comparison still be built for it?

3. A repeat order for a familiar supplier is due within the hour. Why should the full four-step comparison still be run, rather than reusing the supplier's price from the last order?

12Glossary
ENARFRTRMeaning
Comparison sheetورقة المقارنةFiche de comparaisonKarşılaştırma tablosuThe single working document that records an RFQ's facts, each supplier's quotation, the normalised prices, and the estimated risk, ending in one recommendation.
Recommendation lineسطر التوصيةLigne de recommandationTavsiye satırıThe one sentence at the end of a comparison sheet stating which supplier is chosen and the main reason.
Sourcing decisionقرار التوريدDécision d'approvisionnementTedarik kararıThe final choice of which supplier to place an order with, made after price, terms and risk have all been weighed.
Repeat orderطلبية متكررةCommande répétéeTekrar siparişA new order for a style the buyer has already produced before, often with the same or a similar supplier.
Fixed FOB targetهدف سعر FOB الثابتObjectif FOB fixeSabit FOB hedefiA total price the buyer states it is aiming for, used as a benchmark even before a full cost breakdown is agreed, as with Order B (jeans)'s USD 9.80.
Audit trailسجل التدقيقPiste d'auditDenetim iziThe record, kept on the comparison sheet itself, of what each supplier quoted and why one was chosen, so the decision can be reviewed later.
13Next

Course 3, Lesson 1

This is the last lesson of Course 2. The next course builds on a completed, decided supplier comparison to teach what happens once a purchase order is placed with the chosen supplier. Back to the course map

14Ladder

RecognizeName the four steps of a complete quotation comparison, in order.
ConnectSee why a repeat order still needs its own fresh comparison.
CompareTell a provisional, price-only recommendation from a fully supported one.
DecideBuild and record one complete comparison, ending in a recommendation line, for a new order.