Level: PractitionerTime: 45 minutesOrder used: A (the T-shirt, domestic ex-factory version)Tool: Quotation comparison sheet
This lesson is for anyone who must place two quotations stated on different terms side by side, most often a domestic buyer's own purchasing team. Lessons 2.1 and 2.2 are the prerequisites. Money figures are teaching examples in US dollars.
Domestic brandCedar & Co. (12 shops, Make to Stock)
Regular supplierDelta Garments (garment factory)
ProductBasic cotton T-shirt, one colour
Quantity6,000 pieces for one stock replenishment
Payment terms asked60-day open account
DocumentTwo quotations on different bases, to be normalised
02Opening

This page teaches how to adjust two quotations stated on different terms onto one common basis, for anyone whose two incoming quotes cannot be compared as printed

Lesson 2.2 showed that two quotations for the same RFQ often differ in quantity, inclusions, exclusions and validity period, and that these differences must be read before price is compared. Normalising goes one step further: it means recalculating each quotation onto one shared basis, so that a price stated ex-factory, at a different quantity, or with a different payment term, is converted into a figure that means the same thing as the other quote it is being placed against. Omar, the owner of Cedar & Co., does this every time he compares his regular supplier's price against a new factory's offer. This lesson mainly teaches the money flow: converting two prices onto one basis before subtracting one from the other means anything.

03Before you start

What you need, and what this lesson does not cover

You need: the four quotation-reading checks from lesson 2.2, and the delivery-basis vocabulary from Track 11 course 6 and Track 12 course 1.

By the end of this lesson you can:

  • convert an ex-factory price and an FOB price onto the same delivery basis;
  • adjust a quotation given for one quantity to the quantity actually needed, where a per-unit rate is stated;
  • state why payment terms change the real cost of an otherwise identical price;
  • recognise when a normalised comparison, not the printed prices, is the number a decision should be based on.

Not covered here: weighing a normalised price against lead time and quality history (lesson 2.4), and building a full comparison sheet (lesson 2.5).

04Key terms

Words you will meet in this lesson

TermMeaning
NormalisingAdjusting two or more quotations so they are stated on the same delivery terms, quantity, and payment terms before their prices are compared.
Ex-works (EXW)The supplier makes the goods available at its own premises; the buyer arranges and pays for all transport from there.
Delivered priceA price that already includes moving the goods to the buyer's own premises, unlike an ex-works price.
Open accountA payment term where the buyer pays the supplier a set number of days after delivery or invoice, rather than in advance.
Cost of creditThe value to the buyer of being allowed to pay later, or the cost to the supplier of waiting to be paid, often estimated from a standard interest rate.
Common basisThe single set of delivery terms, quantity and payment terms that every quotation is converted to before being compared.
05Teaching
The rule

A quotation is only ready to compare once its delivery terms, quantity and payment terms are converted to match the basis used for every other quotation in the comparison

Two quotations stated on different terms cannot be subtracted from each other and produce a meaningful gap, because a lower price on weaker terms is not automatically a lower real cost. Normalising means picking one common basis, usually the basis closest to what the buyer actually needs, and converting every other quotation to match it: adding transport cost to an ex-works price to make it a delivered price, scaling a quoted rate to the buyer's actual quantity, and adjusting for payment terms when one supplier asks for payment in advance and another offers 60-day open account. Only once every quotation sits on the same basis does the difference between them mean what it appears to mean.

Supplier X's ex-works price: 2.60 USD per piece, plus estimated delivery to Cedar & Co.'s warehouse 0.15 = delivered price 2.75
What you meet in real life

What needs normalising, and by how much, varies by delivery basis, by quantity, and by how the two suppliers set their payment terms

What can differThe shapes you will meetWhy it matters to you
Delivery basisAn export FOB quote already includes moving goods to the port; a domestic ex-works quote does not include moving goods anywhere. Cedar & Co. regularly compares an ex-works quote against a delivered quote from a different supplier.Comparing an ex-works price directly against a delivered price without adding transport cost understates the ex-works supplier's real price.
Quantity quoted versus quantity neededA supplier may quote a per-piece rate valid at 10,000 pieces, while Cedar & Co. only needs 6,000 for one replenishment. Some suppliers hold the same rate at any quantity above a floor; others step the rate up for smaller runs.Applying a large-quantity rate to a smaller actual order can understate the real price the buyer would pay at the quantity it actually needs.
Payment termsA supplier offering 60-day open account is effectively lending the buyer money for those 60 days; a supplier demanding payment in advance is not. Both may quote the identical unit price.Two identical prices on different payment terms are not equally costly to the buyer once the value of that credit period is counted.
Domestic MTS replenishment versus export MTO ordersCedar & Co. buys in smaller, more frequent replenishment quantities to match its own sales forecast, an MTS pattern. Northline Apparel buys the full order quantity once, an MTO pattern.The normalising method is identical either way, but the quantity a rate is being scaled to differs by business model, so the same supplier's quote can normalise differently for two different buyers.
The case we follow

Omar at Cedar & Co. normalises two quotations for a 6,000-piece T-shirt replenishment before deciding which supplier to use

Cedar & Co. buys T-shirts from Delta Garments on 60-day open account, ex-factory pricing, as its regular arrangement. A new supplier has offered a lower price, but on different terms, so Omar converts both to the same basis before comparing.

Basis pointDelta Garments (regular)New supplierNormalised to Cedar & Co.'s basis
Stated price2.80 ex-factory2.60 ex-worksBoth already ex-works/ex-factory; same basis
Quantity stated for6,000 pieces (as needed)10,000 piecesNew supplier's rate at 6,000: confirmed unchanged by new supplier, 2.60 stands
Payment terms60-day open accountPayment in advanceNew supplier's advance payment carries a real cost to Cedar & Co. (worked below)
The worked number

Payment in advance has a real cost even when the quoted unit price is lower, once the value of the credit period Delta Garments offers is counted

Order value at the new supplier's price: 6,000 pieces x 2.60 = 15,600 USD, paid in advance
Estimated cost of Cedar & Co. borrowing 15,600 USD for 60 days at an annual rate of 12%: 15,600 x 0.12 x (60/365) = 307.73 USD
New supplier's price, with the cost of paying in advance added back: 15,600 + 307.73 = 15,907.73 USD, or about 2.65 USD per piece
Delta Garments' order value on 60-day open account, no advance-payment cost: 6,000 x 2.80 = 16,800 USD
Ex-works price versus price with payment-term cost addedNew supplier headline 2.60New supplier normalised 2.65Delta Garments, 60-day terms 2.80
A lower price with weaker payment terms is not automatically the cheaper real offer. Adding the value of the credit period narrows the gap before Omar decides.
The method

Normalise two or more quotations in four steps before comparing their prices

  1. Choose the common basis: the delivery terms, quantity and payment terms the comparison will use.
  2. Convert each quotation's delivery basis to match, adding transport or shipping cost where a quote does not already include it.
  3. Scale each quotation's price to the actual quantity needed, where the supplier's own rate changes by volume.
  4. Adjust for payment terms, adding an estimated cost of credit where one quotation asks for earlier payment than another.
The trap

A common mistake is comparing two quoted unit prices directly, without normalising delivery terms, quantity or payment terms first

A buyer working quickly often takes the two printed unit prices and picks the lower one, treating "ex-works" versus "delivered" or "advance payment" versus "60-day open account" as fine print rather than facts that change the real number. A price that looks 0.20 cheaper on the label can normalise to only 0.15 cheaper, or even more expensive, once transport, quantity scaling and payment terms are added back. Skipping normalisation risks choosing the supplier whose paperwork looks cheapest rather than the one whose real delivered cost, on the terms the buyer actually needs, is cheapest.

Printed prices onlyPrices normalised2.60 ex-works looks 0.20cheaper than 2.80 ex-factory, on the label alone.Once advance-payment costis added, the real gap isabout 0.15, not 0.20.
A printed price gap is not the real gap until every term is converted. Normalising can narrow, or even reverse, what the label alone appears to show.
06In plain words

Two prices from two suppliers cannot just be subtracted from each other if they are not really priced the same way. One might not include delivery to the buyer's own warehouse. One might be priced for a bigger quantity than the buyer actually needs. One might ask to be paid earlier than the other. Normalising means adjusting both prices so they stand for the same real thing, adding back whatever one price leaves out, before deciding which one is genuinely cheaper for the buyer to actually pay.

07Quick check
  • Normalising means converting every quotation to the same delivery terms, quantity and payment terms before comparing price.
  • An ex-works price needs transport cost added to compare against a delivered price.
  • A rate quoted for a larger quantity may not hold at a smaller actual quantity; confirm before using it.
  • Payment terms have a real, estimable cost: earlier payment is worth something to the supplier and costs the buyer something.
  • A lower unit price on weaker payment terms is not automatically the cheaper real offer.
  • The normalising method is the same for domestic MTS replenishment orders and export MTO orders.
08Workplace scenario

Omar is asked to switch to the new supplier because its price is 0.20 lower than Delta Garments' price

Cedar & Co.'s buying assistant recommends switching the T-shirt replenishment to the new supplier, pointing out that 2.60 is 0.20 cheaper than Delta Garments' 2.80.

Here is the comparison the assistant is looking at:

Quotation summary, T-shirt replenishment. Delta Garments: 2.80 ex-factory, 60-day open account. New supplier: 2.60 ex-works, payment in advance. Stated difference: 0.20 per piece in the new supplier's favour.

Should Omar switch suppliers on this comparison alone? Decide before opening the answer.

Show decision

No, not on this comparison alone. Two facts decide this.

First, the new supplier's price assumes payment in advance, not the 60-day open account Delta Garments already offers. Estimating the cost of paying 15,600 USD 60 days earlier, at a 12% annual rate, adds about 307.73 USD to the order, or about 0.05 per piece.

Second, once that cost is added back, the new supplier's normalised price is about 2.65, not 2.60. The real gap against Delta Garments' 2.80 narrows to about 0.15 per piece, not the 0.20 the printed prices suggested.

Omar can still choose the new supplier if 0.15 per piece is worth it to him, but the decision should be made on the normalised gap of about 0.15, not the printed gap of 0.20.

09What it costs

Deciding on the unnormalised price risks giving up cash-flow value worth real money on every replenishment order

Framed with the figures already worked out, switching suppliers on the printed 0.20 gap alone would overstate the saving by about 0.05 per piece, the estimated cost of the payment-terms difference. Repeated across several replenishment orders a year, this gap compounds into a real, avoidable cash-flow cost that a five-minute normalisation would have caught before the decision was made.

Overstated saving per replenishment order of 6,000 pieces: 0.05 x 6,000 = 300 USD understated cost, close to the 307.73 USD calculated above
10Working template

Quotation comparison sheet: use the "Normalise" tab to convert delivery terms, quantity and payment terms onto one basis

Open the Quotation comparison sheet workbook linked below. Its "Normalise" tab lists the four normalising steps this lesson teaches, with Cedar & Co.'s own replenishment example filled in. Fill in the yellow "Your quotes" columns with your own two quotations' delivery terms, quantity and payment terms before comparing any prices.

[Download the Quotation comparison sheet](../../templates/T13-C02-quotation-comparison-sheet.xlsx)

Download the Quotation comparison sheet (Excel)

11Check yourself

1. What does normalising two quotations mean?

2. A supplier quotes 2.60 per piece payable in advance, instead of the buyer's usual 60-day open account. What should be added to make this comparable to a 60-day-terms quote?

3. A supplier's ex-works price is quoted for 10,000 pieces, but the buyer only needs 4,000. What must be checked before using that quoted rate in a comparison?

12Glossary
ENARFRTRMeaning
Normalisingتسوية عروض الأسعارNormalisation des devisTekliflerin normalleştirilmesiAdjusting two or more quotations so they are stated on the same delivery terms, quantity, and payment terms before their prices are compared.
Ex-works (EXW)تسليم من المصنع (EXW)Départ usine (EXW)Fabrika teslim (EXW)The supplier makes the goods available at its own premises; the buyer arranges and pays for all transport from there.
Delivered priceالسعر شاملاً التسليمPrix livréTeslim fiyatıA price that already includes moving the goods to the buyer's own premises, unlike an ex-works price.
Open accountحساب مفتوحCompte ouvertAçık hesapA payment term where the buyer pays the supplier a set number of days after delivery or invoice, rather than in advance.
Cost of creditتكلفة الائتمانCoût du créditKredi maliyetiThe value to the buyer of being allowed to pay later, or the cost to the supplier of waiting to be paid, often estimated from a standard interest rate.
Common basisالأساس الموحد للمقارنةBase commune de comparaisonOrtak karşılaştırma esasıThe single set of delivery terms, quantity and payment terms that every quotation is converted to before being compared.
13Next

Lesson 2.4: Weighing price against lead time and quality history when they disagree

You now know how to bring two quotations onto the same price basis. The next lesson shows what to do once the cheapest normalised price and the most reliable lead time and quality history point to two different suppliers. Back to the course map

14Ladder

RecognizeName the three things a normalised comparison must put on the same basis.
ConnectSee why payment terms have a real, estimable cost even at an identical unit price.
CompareTell a printed price gap from the normalised gap once terms are converted.
DecideJudge which supplier is really cheaper once delivery, quantity and payment terms are normalised.