Advanced · Course 5: Capacity and Order Booking · Lesson 2 of 5

Booking an order across multiple lines when one line alone cannot meet the date

Level: AdvancedTime: 45 minutesOrder used: A (the T-shirt)Tool: Order booking planner
This lesson is for a merchandiser or production manager who must fit one order across more than one line because a single line's free capacity is not enough. Line and quantity figures are illustrative teaching examples; no split-order figure here is a fixed master-cast fact.
FactoryDelta Garments
Line 1 free capacity, that week4,188 pieces (illustrative)
Line 2 free capacity, that week2,712 pieces (illustrative)
Order requested through Meridian Sourcing6,900 pieces, same week
Combined free capacity, both lines6,900 pieces (illustrative)
Split confirmed4,188 to Line 1, 2,712 to Line 2
02Opening

This page explains how to book one order across more than one line when a single line's free capacity cannot cover it alone, and how much of it goes to each line

This page is for anyone who has confirmed, using lesson 11.5.1's method, that a single line's free capacity is not enough for an order it must still fit somewhere. This lesson mainly teaches a decision: which lines together can cover the order's full quantity, and how much of it is booked to each. It builds directly on comparing a requested quantity against free capacity, now applied to more than one line at once.

This matters most at a factory like Delta Garments, where an agent such as Meridian Sourcing, representing a European buyer, may bring an order too large for any one line's free capacity that week, even though the factory as a whole has room for it once two lines are counted together.

Without checking each line's own free capacity separately, a merchandiser can either turn away an order the factory can actually cover, or promise a single line more than it can deliver. This lesson gives the method: find the free capacity on each candidate line, add those free capacities together, and only then decide how much of the order's quantity each line will carry.

03Before you start

What you need, and what this lesson does not cover

You need: the free-capacity method from lesson 11.5.1, applied separately to each line being considered. You do not need to have split an order across lines before.

By the end of this lesson you can:

  • calculate the free capacity of each candidate line for the week an order needs;
  • add two or more lines' free capacities together to check whether they can cover an order's full quantity;
  • decide how much of the order's quantity is booked to each line so none exceeds its own free capacity;
  • confirm that the split lines' booked quantities together equal the order's full requested quantity;
  • avoid the common mistake of checking an order's full quantity against only one line's free capacity and declaring it impossible.

Not covered here: deciding whether to accept a new order in the first place (lesson 11.5.1), reworking a plan once a live order already split across lines has its own critical path slip (lesson 11.5.3), and weighing a rush order against work already booked around it (lesson 11.5.4).

04Key terms

Words you will meet in this lesson

TermMeaning
Booking sheetA shared record that lists which lines are committed to which orders, in which weeks, and how much of each line's capacity each commitment uses, so every booking can be checked against the same total.
Capacity utilisationThe share of a factory's available capacity actually being used by confirmed orders, expressed as a percentage of its maximum output.
Pre-negotiated capacityFactory production capacity a buyer reserves ahead of a season, before a specific order is confirmed.
Make to Order (MTO)Production starts only after a specific buyer has confirmed a specific order, with quantity, price and delivery date agreed.
05Teaching
The rule

An order too large for one line's free capacity is booked across more than one line, with each line's own share never exceeding its own free capacity

An order that exceeds a single line's free capacity can still be fully booked if it is split across two or more lines, provided each line's own share of the order stays within that line's own free capacity for the week in question. The lines' free capacities are added together only to check that the order can be covered at all; the actual booking is still made line by line, each share checked against its own line's free capacity, never against the combined figure alone.

4,188 + 2,712 = 6,900

Combined free capacity across Line 1 and Line 2 for the week: each line's own free capacity, added together to check the order can be covered.

This weekPiecesLine 1 free capacity4,188Line 2 free capacity2,712Combined free capacity, both lines6,900Requested through Meridian Sourcing6,900
Two lines' free capacities are added together only to check whether the order fits at all. Line 1's 4,188 pieces plus Line 2's 2,712 pieces exactly equal the 6,900-piece order requested, but the order is still booked as two separate rows, one per line.
What you meet in real life

A split order can meet different limits depending on how many lines are candidates and who placed the order

A merchandiser who has only ever booked an order to one line should not assume every order that is too big can automatically be split. What differs is how many lines have free capacity that week and how their combined free capacity compares to the order.

What can differThe shapes you meetWhy it matters
Two lines, combined free capacity exactly covers the orderEach line takes a share, and the two shares add up to the order's full quantity with nothing left over.The simplest split, the baseline the method scales up from.
Two lines, combined free capacity exceeds the orderEither line could take a smaller share, and the merchandiser can choose the split, for example favouring the line with more remaining free capacity afterwards.The order can be split in more than one valid way; the check is still that no line's share exceeds its own free capacity.
Two lines, combined free capacity still falls shortEven added together, the lines cannot cover the order's full quantity that week.The order can only be partly accepted across both lines, or a third line or a different week must be found.
An export order placed through an agent such as Meridian SourcingThe agent represents a European buyer and may ask for the split to be confirmed line by line, since its own buyer will want to see which line makes which portion.The split must be recorded clearly enough that each line's own share is traceable, not just a single combined total.
A domestic Make to Stock order split across linesA domestic brand such as Cedar & Co. may have its run split across lines simply because free capacity that week happens to sit on more than one line, not because of any buyer request.The same combined-free-capacity check applies whether the split is buyer-driven or simply where the free capacity happens to be.
The case we follow

Delta Garments' Line 1 and Line 2, each with free capacity checked separately, booked together against an order placed through Meridian Sourcing

Following on from lesson 11.5.1, Line 1 at Delta Garments has 4,188 pieces of free capacity in a given week. Line 2, carrying its own existing booking of 4,200 pieces against a weekly capacity of 6,912 pieces, has 2,712 pieces of free capacity in the same week. Meridian Sourcing, the agent for a European buyer, places an order for 6,900 pieces needed in that same week.

FactWhat it tells the merchandiser
Line 1's free capacity that week4,188 pieces (from lesson 11.5.1)
Line 2's weekly capacity, about 6,912 pieces (illustrative), minus 4,200 pieces already bookedLine 2's free capacity, 2,712 pieces
Combined free capacity across both lines4,188 + 2,712 = 6,900 pieces
Meridian Sourcing's order, requested quantity6,900 pieces, exactly matching the combined free capacity
The worked number

Meridian Sourcing's 6,900-piece order, split across Line 1 and Line 2 so neither line's share exceeds its own free capacity

This example is illustrative, not a claimed fixed academy fact: Line 2's actual weekly capacity is about 6,912 pieces; with 4,200 pieces already booked that week, its free capacity is 6,912 − 4,200 = 2,712 pieces. Added to Line 1's own free capacity of 4,188 pieces, the two lines together have 4,188 + 2,712 = 6,900 pieces of free capacity, exactly matching Meridian Sourcing's 6,900-piece order, so the full order can be booked, with 4,188 pieces to Line 1 and 2,712 pieces to Line 2.

6,912 − 4,200 = 2,712

Line 2's free capacity that week: actual weekly capacity minus what is already booked to it.

4,188 + 2,712 = 6,900

The two lines' free capacities added together, exactly covering the order's full requested quantity.

Line 1: 4,188Line 2: 2,712Line 1's 4,188 pieces plus Line 2's 2,712 pieces together equal Meridian Sourcing's full 6,900-piece order.
The order is split so each line's share exactly matches that line's own free capacity. Line 1 carries 4,188 pieces and Line 2 carries 2,712 pieces, neither exceeding its own free capacity, and the two shares together equal the full order.
The method

How to split one order's booking across more than one line

  1. Calculate the free capacity of each candidate line for the week the order needs, using lesson 11.5.1's method.
  2. Add the candidate lines' free capacities together to check whether their combined free capacity covers the order's full quantity.
  3. Decide each line's share of the order, keeping every line's share within its own free capacity.
  4. Record each line's share as its own row on the shared booking sheet, not as one combined entry.
  5. Confirm the shares add up to the order's full requested quantity, and flag any shortfall if the combined free capacity still falls short.
The trap

Checking an order's full quantity against only one line's free capacity and declaring the order impossible to book

A common mistake is checking an order's full requested quantity against a single line's free capacity, and turning the order away or losing it to another factory when that one line falls short, without checking whether a second line's free capacity that week could cover the rest.

06In plain words

When an order is too big for one line's free room, check whether another line has free room in the same week. Add the two lines' free amounts together to see if, combined, they can cover the whole order. If they can, decide how much of the order each line will make, keeping each line's own share inside its own free room. Write each line's share down separately, not as one shared number. Turning away an order because it does not fit one line, without checking whether a second line's free room could cover the rest, can lose work the factory actually had room for.

07Quick check
  • A single line's free capacity is checked exactly as in lesson 11.5.1, one line at a time.
  • Combined free capacity across two or more lines = each line's own free capacity added together.
  • An order fits across lines only if the combined free capacity is at least the order's full quantity.
  • Each line's own booked share must stay within that line's own free capacity, never the combined figure.
  • Every line's share of a split order is recorded as its own row on the booking sheet.
  • The sum of every line's booked share must equal the order's full requested quantity, with no shortfall unflagged.
08Workplace scenario

Meridian Sourcing places a 6,900-piece order and asks whether Delta Garments can cover it, after Mona finds Line 1 alone can only take 4,188 pieces

Meridian Sourcing places an order for 6,900 pieces, needed in a specific week. Mona checks Line 1 alone using lesson 11.5.1's method, finds its free capacity is only 4,188 pieces, and tells the agent the order cannot be booked, without checking any other line.

  • Line 1's free capacity that week is 4,188 pieces, well short of the 6,900-piece order on its own.
  • Line 2's weekly capacity that same week is about 6,912 pieces, with 4,200 pieces already booked.
  • Line 2's free capacity, once calculated, is 2,712 pieces.

Karim's note to Mona:

"Mona, before you turn Meridian's order away, check whether Line 2 has free room the same week. One line falling short doesn't mean the factory can't cover it."

Is it correct for Mona to declare the order impossible to book after checking only Line 1's free capacity of 4,188 pieces?

Show decision

No. Mona must also check Line 2's free capacity for the same week: its weekly capacity of about 6,912 pieces minus the 4,200 pieces already booked gives 2,712 pieces free. Added to Line 1's 4,188 pieces, the two lines together have 6,900 pieces of free capacity, exactly matching the order.

First, an order that exceeds one line's free capacity is not automatically impossible, since another line may have free capacity the same week.

Second, 4,188 plus 2,712 equals 6,900, so the full order can be booked with 4,188 pieces on Line 1 and 2,712 pieces on Line 2.

Mona should confirm the order to Meridian Sourcing as fully bookable, split across both lines, rather than declining it on the basis of Line 1 alone.

09What it costs

The cost of declining an order the factory could actually cover by splitting it across two lines

If Mona had declined Meridian Sourcing's order after checking only Line 1, the factory would lose the whole 6,900-piece order to another supplier, even though its own combined free capacity across two lines exactly matched what was requested.

6,900 × 3.20 = 22,080.00

One illustrative measure of the lost order's value, in USD: the order's 6,900 pieces at Order A's own fixed FOB price of USD 3.20 per piece, reused illustratively to show the scale of a wrongly declined order.

Beyond the value of this one order, a supplier that turns away work it can actually cover risks losing the buyer's future orders too, since an agent or buyer who is wrongly told "no room" has no reason to check back before placing the next order elsewhere.

10Working template

Order booking planner: the "Split Across Lines" sheet

This lesson uses the "Split Across Lines" sheet of the course's Order booking planner, which reads each candidate line's actual weekly capacity and existing bookings, calculates each line's free capacity, and lets you record how much of a split order is booked to each line. Enter each line, the week, and the share booked to it, and let the sheet total the shares against the order's full quantity. Download link: the course tool, `templates/T11-C05-order-booking-planner.xlsx`.

Download the Order booking planner (Excel)

11Check yourself

1. Line 1 has 4,188 pieces free and Line 2 has 2,712 pieces free in the same week. An order requests 6,900 pieces that week. Can it be booked?

2. Line 1 has 2,000 pieces free and Line 2 has 1,500 pieces free in the same week. An order requests 4,000 pieces. What is correct?

3. Why is each line's share checked against that line's own free capacity, not only the combined free capacity of all lines?

12Glossary
ENARFRTRMeaning
Booking sheetورقة الحجزFiche de réservationRezervasyon tablosuA shared record that lists which lines are committed to which orders, in which weeks, and how much of each line's capacity each commitment uses, so every booking can be checked against the same total.
Capacity utilisationمعدل استغلال الطاقة الإنتاجيةTaux d'utilisation de la capacitéKapasite kullanım oranıThe share of a factory's available capacity actually being used by confirmed orders, expressed as a percentage of its maximum output.
Pre-negotiated capacityطاقة إنتاجية محجوزة مسبقًاCapacité pré-négociéeÖnceden ayrılmış kapasiteFactory production capacity a buyer reserves ahead of a season, before a specific order is confirmed.
Make to Order (MTO)الإنتاج حسب الطلبFabrication sur commande (MTO)Siparişe göre üretim (MTO)Production starts only after a specific buyer has confirmed a specific order, with quantity, price and delivery date agreed.
13Next

Lesson 11.5.3: Reworking a capacity plan when a live order's critical path slips

You now know how to split one order's booking across more than one line's free capacity so its full quantity still fits. The next lesson looks at what happens to a booking plan already built this way when a live order's own critical path slips and its production weeks shift. Back to the course map

14Ladder

RecognizeName what combined free capacity across lines shows and what it does not show.
ConnectSee why each line's share must still be checked against that line's own free capacity.
CompareTell an order that genuinely cannot be covered from one that only looked that way on a single line.
DecideSplit an order's booking across lines so every line's share fits its own free capacity.