This page explains phasing: dividing a total forecast quantity into weekly delivery amounts that follow a style's own real selling pattern, instead of shipping the whole forecast in one delivery regardless of when it will actually sell. It is for a factory or buyer turning a confirmed total forecast into a week-by-week delivery plan.
At work, a factory such as Delta Garments and a buyer such as Northline Apparel agree a total forecast quantity, but a single delivery of that whole quantity on one date creates its own problem: a style that sells more heavily in the early weeks of a season needs more stock in shops early, while a style that builds steadily needs a more even supply across the season. Delivering the entire forecast at once, on one date chosen for production convenience rather than the selling pattern, risks shops running short in heavy-selling weeks while still holding excess stock in slower ones. This lesson gives you the method for phasing a confirmed forecast to match a style's own real selling pattern.
You need: lesson 3.1's forecast for Order A's own T-shirt is useful background but not required.
By the end of this lesson you can:
Not covered here: building the forecast total itself from sales history (lesson 3.1); adjusting the phased plan once real sales data starts coming in (lesson 3.3).
| Term | Meaning |
|---|---|
| Phasing | Spreading a total forecast quantity across the weeks of a season, timed to a style's own real selling pattern rather than delivered as one lump sum. |
| Selling pattern | The share of a style's own total season sales that falls in each week, based on its own recorded sales history. |
| Front-loaded | A selling pattern where a larger share of a style's own total sales falls in the earlier weeks of a season. |
| Delivery drop | A scheduled point in a season when a phased quantity of a style is delivered to the shop. |
| Intake | The quantity of a style planned to arrive in shops in a given week of a season, as set by the phasing plan. |
| Lead time | The total time from a confirmed order to the goods reaching their destination. |
Phasing takes a style's own total forecast and spreads it across the weeks of a selling season in shares that match its own selling pattern: the proportion of total sales that genuinely falls in each week, based on recorded history. A style that is front-loaded, selling more heavily in its early weeks, needs a larger intake early in the season; a style that sells steadily needs a more even weekly supply instead. Phasing turns a single total number into a week-by-week plan that a factory can actually deliver against.
| What can differ | The shapes you will meet | Why it matters |
|---|---|---|
| Export, Make to Order, factory-led | Delta Garments phases Order A's own confirmed forecast into shipments timed to Northline Apparel's own front-loaded selling pattern, within the order's fixed 16-week production timeline. | A factory phasing deliveries must still work inside its own fixed production lead time; phasing decides delivery timing, not production speed. |
| Domestic, Make to Stock, buyer-led | Cedar & Co. phases its own standing forecast into a steady weekly reorder quantity, since its basic style sells at a roughly even rate across the season rather than front-loaded. | A steady selling pattern calls for even phasing; forcing an even style into a front-loaded plan would create unnecessary early-season excess stock. |
| A style with two selling peaks | A style that sells heavily both at season launch and again around a mid-season promotion needs two separate phased peaks in its intake, not one. | A selling pattern is not always a single front-loaded curve; some styles genuinely have more than one peak that phasing must reflect. |
| A style constrained by lead time, not demand | A style whose weekly demand would call for an earlier delivery than the factory's own fixed lead time allows must be phased against what is actually achievable, with the gap flagged rather than hidden. | Phasing works within a real production lead time; it cannot deliver a quantity before the factory can genuinely produce it. |
Delta Garments and Northline Apparel take the 14,413-piece total forecast from lesson 3.1 and phase it into three deliveries across the selling season, rather than shipping the whole quantity on one date. Northline Apparel's own recorded selling pattern for the style shows 45% of a season's sales in the first four weeks, 35% in the next four weeks, and 20% in the remaining weeks, a genuinely front-loaded pattern. Delta Garments phases the three deliveries to match these shares, each still fitting inside Order A's own fixed 16-week production timeline.
| Question | One lump-sum delivery | Phased into three deliveries |
|---|---|---|
| What happens in the season's first four weeks? | Shops hold the full 14,413 pieces from day one, ahead of most of the season's own demand | Shops receive close to 45% of the forecast, matching the season's own heaviest selling weeks |
| What happens to stock still unsold late in the season? | A large, undifferentiated stock position with no phased visibility into what is selling when | A smaller final delivery, sized to the season's own slower final weeks |
| Who can tell whether the pattern is holding? | Nobody, since one lump delivery gives no weekly reference points to check against | Northline Apparel and Delta Garments, since each phased delivery is a checkable milestone |
Delta Garments applies Northline Apparel's own 45%, 35% and 20% selling-pattern shares to the 14,413-piece total forecast to size each phased delivery.
A common mistake is dividing a total forecast into equal weekly or period amounts without checking whether the style's own selling pattern is actually even. If Delta Garments had phased Order A's own 14,413-piece forecast into three equal deliveries of about 4,804 pieces each, ignoring Northline Apparel's own genuinely front-loaded 45/35/20 pattern, the first delivery would undersupply the season's own heaviest-selling weeks while the third delivery oversupplies its slowest ones, the opposite of what the real selling pattern calls for.
Once a buyer and factory agree a total forecast quantity, they still need to decide when that quantity arrives, not just how much of it there is. A style rarely sells at an even rate across a whole season; some styles sell more heavily early, some build steadily, and some have more than one peak. Phasing takes the style's own real selling pattern from its sales history and uses it to size separate deliveries across the season, so more stock arrives in weeks that genuinely sell more and less arrives in weeks that genuinely sell less. Every phased delivery must still fit inside the factory's own real production lead time, and all the phased deliveries must add back up to the original total forecast.
Northline Apparel plans an early-season promotion and asks Delta Garments whether Delivery 1 can be increased from 6,486 pieces to 8,000 pieces, with the difference taken from Delivery 2.
Should Delta Garments move 1,514 pieces from Delivery 2 into Delivery 1 to support the early promotion? Decide before you open the answer.
No, not without reworking an already-committed fabric stage. Phasing a forecast into deliveries is only useful if each delivery's own production commitments, such as fabric, are then planned against the phased figures; changing a delivery's size after fabric is already committed undoes that planning.
First, what the fabric commitment already reflects. Order A's own 5-week fabric stage for Delivery 1 was placed against the 6,486-piece figure; increasing it to 8,000 pieces mid-stage means sourcing additional fabric for pieces not yet committed, inside a timeline that assumed the original split.
Second, what the real alternative is. Northline Apparel's promotion can proceed on the 6,486 pieces already phased into Delivery 1, since that figure was itself sized to the season's own heaviest-selling weeks; the promotion does not require pulling stock forward from a delivery whose own fabric commitment has already been placed.
Delta Garments should hold the original three-delivery phasing plan and confirm Delivery 1's existing 6,486 pieces are sufficient for the promotion, rather than reworking a fabric commitment already placed against the current split. Lesson 3.3 covers how to adjust a phased plan once real sales data, rather than a planned promotion, calls for a genuine change.
Framed in time and cost rather than a single penalty figure: Order A's own fixed timeline allows 5 weeks for fabric, already committed against Delivery 1's original 6,486-piece figure.
Sourcing an additional 310 kg of fabric mid-stage, after the original 5-week fabric commitment is already placed, risks pushing the fabric stage past its own fixed 5 weeks, which shifts every later stage of Order A's own fixed 16-week timeline by the same delay. A phasing change made without checking the production stage behind it converts a scheduling request into a real risk to the entire order's own delivery date.
The workbook's "Phasing" sheet takes the total forecast from the "Sales history and forecast" sheet, applies each selling-pattern share entered by week or period, calculates each phased delivery quantity, and checks that all phased deliveries sum back to the original total forecast.
Delta Garments' own rows record the 45%, 35% and 20% shares against Order A's own 14,413-piece forecast, with the sheet calculating 6,486, 5,045 and 2,882 pieces and confirming the three sum to the original total.
1. Why is a total forecast phased across a season's weeks instead of delivered as one lump sum?
2. Northline Apparel's style sells 45% of its season total in weeks 1–4. What is Delivery 1's quantity from a 14,413-piece total forecast?
3. Northline Apparel asks to move 1,514 pieces from Delivery 2 into Delivery 1 for a promotion, after Delivery 1's fabric is already committed. What should Delta Garments do?
| EN | AR | FR | TR | Meaning |
|---|---|---|---|---|
| Phasing | التوزيع على مراحل | Phasage | Aşamalandırma | Spreading a total forecast quantity across the weeks of a season, timed to a style's own real selling pattern rather than delivered as one lump sum. |
| Selling pattern | نمط البيع | Schéma de ventes | Satış deseni | The share of a style's own total season sales that falls in each week, based on its own recorded sales history. |
| Front-loaded | متقدم البيع | À vente anticipée | Öne yüklü | A selling pattern where a larger share of a style's own total sales falls in the earlier weeks of a season. |
| Delivery drop | دفعة تسليم | Livraison échelonnée | Teslimat partisi | A scheduled point in a season when a phased quantity of a style is delivered to the shop. |
| Intake | الوارد | Arrivage | Mal girişi (intake) | The quantity of a style planned to arrive in shops in a given week of a season, as set by the phasing plan. |
| Lead time | الوقت الإجمالي للتنفيذ | Délai de production | Teslim süresi | The total time from a confirmed order to the goods reaching their destination. |
You now know how to phase a forecast across weeks to match a real selling pattern. The next lesson covers what happens once the season actually starts and real sales data begins arriving. Back to the course map