Practitioner · Course 3: Forecasting and Phasing · Lesson 5 of 5

Building a complete forecasting and phasing worksheet

Level: PractitionerTime: 45 minutesOrder used: Order A's own T-shirt style, ordered by Cedar & Co. under a hybrid standing-forecast arrangementTool: Forecasting and phasing worksheet
For a buyer or planner assembling a complete forecasting and phasing worksheet from the sheets built across this course. Lessons 3.1 to 3.4 are useful background, not required. Cedar & Co.'s figures are a teaching example, not reported company data.
BuyerCedar & Co., under a hybrid arrangement with Delta Garments
Hybrid split3,000 pieces standing forecast, 1,200 confirmed later
What this lesson assemblesForecast, phasing, re-forecast and cost check as one worksheet
StyleOrder A's T-shirt, sold domestically by Cedar & Co.
Order A's own fixed figuresIts own 3.20 / 19.90 / 3.98 price points
After this lessonApplying this worksheet to a new style each season
02Opening

This page explains how to assemble a complete forecasting and phasing worksheet, bringing the forecast, the phased plan, the re-forecast check and the cost comparison into one place for a single style

This page explains how the four separate pieces built across this course, a sales-history forecast, a phased weekly plan, a re-forecast check, and a cost comparison between over- and under-forecasting, come together into one complete worksheet for a real style. It is for a buyer, planner or factory contact who must run all four steps together for a style under a hybrid ordering arrangement.

At work, a buyer such as Cedar & Co. does not use forecasting, phasing, re-forecasting and cost weighing as separate, disconnected exercises; it runs them together, in sequence, for every style it forecasts. Treating them as separate tools that never meet is a real problem: a forecast built without its own phasing plan cannot be delivered against; a phasing plan never checked against real sales cannot be trusted mid-season; and a re-forecast made without knowing which direction of error costs more cannot be set with the right amount of caution. This lesson brings all four pieces together into one worksheet, using a single hybrid order as the example that runs through it.

03Before you start

You need: lessons 3.1 to 3.4's forecasting, phasing, re-forecasting and cost-comparison methods; each is drawn on directly in this lesson.

By the end of this lesson you can:

  • state how a sales-history forecast, a phased plan, a re-forecast check and a cost comparison fit together as one sequence, not four separate exercises;
  • build a complete forecasting and phasing worksheet for a single style from a sales history through to a cost-aware final quantity;
  • apply the method for deciding a hybrid order's own standing-forecast and confirmed-later split using all four pieces together;
  • read the forecasting and phasing worksheet's summary sheet and say what each of its columns draws from;
  • avoid the common mistake of treating the four pieces as independent checks that are never reconciled against each other.

Not covered here: this is the course's final lesson; it assembles the four previous lessons rather than introducing a new method.

04Key terms
TermMeaning
ForecastA company's own estimate of what it expects to sell, used to decide how much to produce before any specific sale exists.
PhasingSpreading a total forecast quantity across the weeks of a season, timed to a style's own real selling pattern rather than delivered as one lump sum.
Re-forecastUpdating the remaining part of a season's forecast once real sales data shows a sustained gap from the original estimate.
Asymmetric costA situation where the cost of one direction of forecast error is genuinely different from the cost of the other direction, for the same style.
Hybrid productionA factory building part of a run to its own forecast before a buyer confirms it, and finishing the rest once the buyer's own order is confirmed.
Reorder pointThe quantity of stock remaining at which a Make to Stock buyer places its next production order against the standing forecast.
05Teaching
The rule

A complete forecasting and phasing worksheet runs a style through four steps in sequence: forecast, phase, re-forecast, and cost-check, not four separate, unconnected exercises

A single style's own ordering plan draws on all four pieces built across this course, in a fixed sequence. First, a forecast built from the style's own sales history. Second, phasing that spreads the forecast across the season's weeks to match its own selling pattern. Third, a re-forecast check once real sales data starts arriving, updating the remaining weeks where a sustained gap is confirmed. Fourth, a cost check using the style's own asymmetric cost, so any caution built into the plan leans toward whichever direction of error is genuinely more expensive. Run in this order, on a real hybrid order, the four pieces become one worksheet rather than four disconnected checks.

Forecast Phasing Re-forecast Cost check
Forecast, phasing, re-forecast and cost check run in a fixed sequence to build one complete worksheet, not four separate checks. Each step draws directly on the one before it.
What you meet in real life

The four-step sequence applies to any style, but a hybrid order runs it against two portions instead of one

What can differThe shapes you will meetWhy it matters
Domestic, hybrid, buyer-ledCedar & Co. commits 3,000 pieces of a style to a standing forecast with Delta Garments, and confirms a further 1,200 pieces only once early sales data supports it.A hybrid buyer runs the full four-step sequence twice in effect: once for the committed portion's phasing, and again for the confirmed-later portion's re-forecast trigger.
Export, Make to Order, single confirmed orderNorthline Apparel runs the same four-step sequence once, before its order is confirmed, since a Make to Order order has little room to re-forecast mid-production.A single confirmed order still benefits from all four steps, even though the re-forecast step mainly informs the next order rather than the current one.
A style with strong asymmetric costA style whose under-forecast cost is nearly three times its over-forecast cost, such as Order A's own T-shirt at Fairway Stores, should be forecast with a deliberate lean toward the higher end of its history-based range.Skipping the cost-check step leaves a forecast set without knowing which direction it should lean toward if genuine doubt exists.
A style with balanced asymmetric costA style where the markdown rate and the margin are closer together carries less reason to lean the forecast in either direction, and can be set closer to the plain history-based average.Not every style needs a deliberate lean; the cost check itself tells a buyer whether one is justified.
The case we follow

Cedar & Co. runs Order A's own T-shirt through all four steps to set its hybrid standing-forecast and confirmed-later split with Delta Garments

Cedar & Co. sells Order A's own T-shirt domestically and arranges a hybrid order with Delta Garments: a 3,000-piece portion committed to a standing forecast built from sales history, and a further 1,200-piece portion confirmed only once early sales data supports it. Cedar & Co. runs the style through forecasting, phasing, re-forecasting and the cost check together to set this split with real numbers behind it, rather than choosing 3,000 and 1,200 as round, unexamined figures.

QuestionTreating the four steps separatelyRunning the four steps as one worksheet
What sets the 3,000-piece committed figure?A round number chosen without reference to sales historyThe style's own history-based forecast, phased across the season
What happens once early sales data exists?No defined trigger for reconsidering the confirmed-later portionThe re-forecast check flags whether the 1,200-piece portion should move
What sets which way the plan leans if in doubt?No defined basis, so the plan might drift either direction by habitThe cost check, showing which direction of error is genuinely more expensive for this style
The worked number

Cedar & Co.'s worksheet moves the confirmed-later portion from 1,200 to 1,340 pieces once the four steps are run together

Cedar & Co.'s worksheet starts from a 4,140-piece history-based forecast (built as in lesson 3.1), phases 3,000 pieces into the standing-forecast portion and 1,140 pieces into the confirmed-later portion, then applies the cost check from lesson 3.4 once early sales data confirms a sustained gap of 140 pieces above the phased plan (as in lesson 3.3).

History-based total forecast: 4,140 pieces
Standing-forecast portion, committed outright: 3,000 pieces
Confirmed-later portion, before re-forecast: 4,140 − 3,000 = 1,140 pieces
Confirmed sustained sales gap (lesson 3.3 method): +140 pieces
Re-forecast confirmed-later portion: 1,140 + 140 = 1,280 pieces
Cost check (lesson 3.4): under-forecast costs more than over-forecast for this style, so the plan rounds up rather than down: 1,280 → 1,300 pieces confirmed
Before re-forecast1,140 pieces After re-forecast1,280 pieces After cost check1,300 pieces
The confirmed-later portion moves from 1,140 to 1,280 pieces once real sales confirm a sustained gap, then to 1,300 once the cost check favours leaning toward the costlier under-forecast direction. Each step changes the figure for a specific, checkable reason.
The method

Six steps that assemble a complete forecasting and phasing worksheet for one style under a hybrid order

  1. Build the total forecast from the style's own sales history, adjusted for any known change. This is the lesson 3.1 method, and it sets the worksheet's own starting figure.
  2. Phase the total forecast into a standing-forecast portion and, for a hybrid order, a confirmed-later portion. Use the style's own selling pattern from lesson 3.2 to size each portion sensibly.
  3. Check real sales against the phased plan once the season begins. Use the lesson 3.3 method to confirm whether a genuine, sustained gap exists.
  4. Re-forecast the confirmed-later portion if a sustained gap is confirmed. Apply the confirmed real rate, not the original assumed rate, exactly as in lesson 3.3.
  5. Run the cost check from lesson 3.4 on the style's own markdown rate and margin. Confirm which direction of error is genuinely more expensive before finalizing any rounding.
  6. Record every step's own figure in the worksheet, in sequence, before the confirmed-later portion is finalized with the factory. Each figure should trace back to the step that produced it, so the whole plan can be checked later.
The trap

A common mistake is running one or two of the four steps well and skipping the rest, rather than treating all four as one connected worksheet

A common mistake is building a careful sales-history forecast and a careful phased plan, then skipping the re-forecast check once the season starts, or skipping the cost check when deciding how to round a confirmed-later portion. If Cedar & Co. had stopped after phasing the 1,140-piece confirmed-later portion, without checking real sales or running the cost check, the 140-piece sustained gap and the style's own asymmetric cost would both go unused, leaving the confirmed-later portion at 1,140 pieces when the fuller picture points to 1,300.

06In plain words

A complete forecasting and phasing worksheet is not four separate tools kept in different places; it is one sequence run for a single style. First, a forecast built from real sales history. Second, a phased plan that spreads that forecast across the season to match how the style actually sells, split further for a hybrid order into a committed portion and a confirmed-later portion. Third, a check of real sales against the phased plan once the season starts, re-forecasting the confirmed-later portion if a genuine, sustained gap appears. Fourth, a cost check that confirms which direction of forecast error is more expensive for this specific style, so any rounding or final lean in the plan favours avoiding the costlier mistake. Run together, in this order, the four steps produce one final, defensible figure rather than four separate, disconnected checks.

07Quick check
  • A complete worksheet runs forecast, phasing, re-forecast and cost check in that order for one style.
  • A hybrid order splits the total forecast into a standing-forecast portion and a confirmed-later portion.
  • Real sales are checked against the phased plan, and the confirmed-later portion is re-forecast only if a sustained gap is confirmed.
  • The cost check decides which direction any final rounding should lean toward, using the style's own markdown rate and margin.
  • Skipping any one of the four steps leaves the worksheet incomplete, even if the other steps were done carefully.
08Workplace scenario

Delta Garments asks Cedar & Co. to confirm the final confirmed-later quantity before its own production slot for the portion closes

Delta Garments' own production slot for Cedar & Co.'s confirmed-later portion closes in three days, and Delta Garments asks for a final quantity.

  • Cedar & Co.'s worksheet has already run all four steps: a 4,140-piece total forecast, a 1,140-piece confirmed-later portion before re-forecast, a confirmed 140-piece sustained gap, and a cost check favouring the higher, under-forecast-avoiding direction.
  • The worksheet's own re-forecast step points to 1,280 pieces; the cost check points to rounding to 1,300 pieces.
  • Delta Garments' own hybrid production arrangement can build any quantity Cedar & Co. confirms within its current slot, but cannot revisit the figure once the slot closes.
Cedar & Co., worksheet note: "Our worksheet runs the portion through forecast, phasing, re-forecast and cost check: 1,140, re-forecast to 1,280 on a confirmed gap, then rounded to 1,300 given this style's own numbers. Confirming 1,300 pieces for the current slot."

Should Cedar & Co. confirm 1,140 pieces, the original phased figure, or 1,300 pieces, the figure after all four worksheet steps? Decide before you open the answer.

Show decision

1,300 pieces, the figure produced by running all four worksheet steps. The original 1,140-piece phased figure was correct at the time it was set, but it predates both the confirmed sustained sales gap and the cost check, both of which are now available and both of which point toward a higher figure.

First, why the re-forecast step changes the figure. A confirmed, sustained 140-piece gap between real sales and the phased plan is exactly the condition lesson 3.3 sets for updating a figure; ignoring it discards real, checkable evidence in favour of an earlier, less-informed number.

Second, why the cost check sets the final rounding direction. This style's own numbers show under-forecasting as the more expensive direction; rounding from 1,280 up to 1,300, rather than down, reflects that specific, calculated asymmetry rather than an arbitrary rounding choice.

Cedar & Co. should confirm 1,300 pieces with Delta Garments before the current production slot closes, since this figure is the one that reflects every step of the worksheet, not just the earliest one. This closes the course: a complete forecast is one that has been phased, checked against real sales, and weighed for its own cost asymmetry before it is finalized.

09What it costs

Confirming the outdated 1,140-piece figure instead of the worksheet's own 1,300-piece figure risks USD 1,904 of avoidable lost margin

Framed using the same cost-check method from lesson 3.4, applied to the gap between the outdated and the fully worked figure.

Fully worked confirmed-later quantity: 1,300 pieces
Outdated phased-only quantity: 1,140 pieces
Shortfall if the outdated figure is confirmed instead: 1,300 − 1,140 = 160 pieces
Cedar & Co.'s own margin per piece (as in lesson 3.4): USD 11.90
Lost margin on the shortfall: 160 × 11.90 = USD 1,904

Confirming the earlier, phased-only figure instead of the fully worked worksheet figure would forgo approximately USD 1,904 of margin on demand the worksheet's own re-forecast and cost-check steps had already identified as real and worth planning for. The four-step sequence exists precisely to catch a gap like this before a production slot closes rather than after.

10Working template

Forecasting and phasing worksheet: the summary sheet this lesson completes

The workbook's "Summary" sheet draws the total forecast from the "Sales history and forecast" sheet, the phased split from the "Phasing" sheet, the re-forecast figure from the "Re-forecast" sheet, and the recommended rounding direction from the "Forecast cost comparison" sheet, presenting one final confirmed-later quantity with each contributing figure still visible beside it.

Cedar & Co.'s own row shows 4,140 pieces total forecast, 3,000 pieces standing-forecast, 1,140 pieces confirmed-later before re-forecast, 1,280 pieces after re-forecast, and 1,300 pieces as the final cost-checked figure confirmed to Delta Garments.

Download the Forecasting and phasing worksheet (Excel)

11Check yourself

1. Why does a complete forecasting and phasing worksheet run forecast, phasing, re-forecast and cost check in sequence rather than as separate, unconnected exercises?

2. Cedar & Co.'s confirmed-later portion was phased at 1,140 pieces, then re-forecast to 1,280 pieces after a confirmed sales gap. What should the cost check do next?

3. Delta Garments' production slot is closing and needs Cedar & Co.'s final confirmed-later quantity. Which figure should Cedar & Co. confirm?

12Glossary
ENARFRTRMeaning
Forecastالتوقع (توقع المبيعات)Prévision (prévision des ventes)Tahmin (satış tahmini)A company's own estimate of what it expects to sell, used to decide how much to produce before any specific sale exists.
Phasingالتوزيع على مراحلPhasageAşamalandırmaSpreading a total forecast quantity across the weeks of a season, timed to a style's own real selling pattern rather than delivered as one lump sum.
Re-forecastإعادة التوقعReprévisionYeniden tahminUpdating the remaining part of a season's forecast once real sales data shows a sustained gap from the original estimate.
Asymmetric costتكلفة غير متماثلةCoût asymétriqueAsimetrik maliyetA situation where the cost of one direction of forecast error is genuinely different from the cost of the other direction, for the same style.
Hybrid productionالإنتاج الهجينProduction hybrideHibrit üretimA factory building part of a run to its own forecast before a buyer confirms it, and finishing the rest once the buyer's own order is confirmed.
Reorder pointنقطة إعادة الطلبPoint de recommandeYeniden sipariş noktasıThe quantity of stock remaining at which a Make to Stock buyer places its next production order against the standing forecast.
13Next

Course 4, Lesson 1: Deciding when a style needs its first markdown

You have completed Course 3's full forecasting and phasing worksheet. Course 4 turns to what happens once a forecast's own surplus needs to be resolved: deciding when a style needs its first markdown. Back to the course map

14Ladder

RecognizeTell a complete, four-step worksheet figure apart from one produced by only a step or two.
ConnectSee how Cedar & Co.'s figure moves from 1,140 to 1,280 to 1,300 as each step is applied.
CompareTell a hybrid buyer's two-portion worksheet apart from a single-order buyer's one-pass version.
DecideConfirm a final quantity only once all four steps have run, not after the first step alone.