Course contents
Practitioner · Course 1: Enquiry to Quotation · Lesson 2 of 5

Building a costed quotation from an enquiry's own specification

Level: PractitionerTime: 45 minutesOrder used: Order A, Northline Apparel's confirmed T-shirt specificationTool: Enquiry-to-quotation tracker
This lesson is for a merchandiser or buyer who needs to see how a confirmed specification becomes a costed quotation, line by line. No earlier lesson is needed beyond lesson 1.1. Figures are teaching figures; the case is Sara at Northline Apparel reading Delta Garments' quotation for Order A's T-shirt.
BuyerNorthline Apparel, export, established relationship
FactoryDelta Garments
Confirmed specification180 GSM T-shirt, 15,000 pieces, standard four-size run
Quotation receivedFOB USD 3.20 per piece, built line by line from the spec
What this lesson coversBuilding and reading a costed quotation's own lines
ToolEnquiry-to-quotation tracker
02Opening

This page teaches a buyer, or a merchandiser thinking from the buyer's side, what a costed quotation's lines must show before it can be trusted

This page teaches a buyer, or a merchandiser thinking from the buyer's side, what a costed quotation's lines must show before the price on it can be trusted. This lesson mainly teaches money: how a confirmed specification turns into a price, cost element by cost element, and what a buyer checks before accepting a number. At work, a buyer who receives only a single FOB figure cannot tell whether that price is fair, whether it will hold if the order grows, or where it might move if a fabric price changes.

Sara, the buyer at Northline Apparel, receives Delta Garments' quotation for the T-shirt enquiry confirmed in lesson 1.1: 15,000 pieces, 180 GSM single jersey, ratio 1:2:2:1. The quotation states one number, FOB USD 3.20 per piece, but Sara's own job depends on knowing what sits behind that number. A quotation that shows only a total price forces the buyer to trust it blindly; a quotation that shows each cost element lets the buyer check it against what it already knows about fabric, trims and making costs. This lesson builds that quotation line by line, from the buyer's own point of view.

03Before you start

What you need, and what this lesson does not cover

You need: lesson 1.1, reading a buyer's enquiry, since this lesson starts from a specification already confirmed.

By the end of this lesson you can:

  • list the cost elements a costed quotation must show, beyond one total price;
  • build a quotation's FOB price from fabric, trims, making, overhead and profit;
  • check whether a quoted price is consistent with an order's own confirmed specification;
  • recognise which cost elements move if the quantity changes, and which stay fixed;
  • read a quotation the way a buyer reads it, not only the way a factory writes it.

Not covered here: setting the quotation's validity, MOQ and lead time (lesson 1.3); presenting the finished quotation and handling the buyer's first questions (lesson 1.4); tracking many quotations across a full order book (lesson 1.5).

04Key terms

Words you will meet in this lesson

TermMeaning
Costed quotationA quotation that shows the price broken into its cost elements, not just one total figure, so the buyer can check how it was built.
Cost elementOne part of a price, such as fabric, trims, making, overhead, or profit, added together to form the full FOB price.
FOB priceFree on board; the price a buyer pays per piece up to the goods being loaded on the ship, before shipping and duty are added.
Making costThe cost of cutting, sewing and finishing a garment, separate from fabric and trims, one of the five lines in a costed quotation.
OverheadThe share of a factory's running costs, such as rent, power and salaries, added to each piece's price on top of fabric, trims and making.
MarginThe profit a factory keeps once every other cost element in the price has been covered.
05Teaching
The rule

A costed quotation adds fabric, trims, making, overhead and profit as separate lines that sum to the FOB price

A costed quotation states the FOB price as the sum of its own cost elements: fabric, trims, making, overhead, and profit, each shown as its own line rather than folded into one number. A buyer who receives a quotation built this way can check each element against what it already knows, ask about the one line that looks out of place, and see clearly what would change if the specification changed. A single total price hides all of this.

Order A's FOB price, USD 3.20 per piece, by cost element Fabric 1.15 Trims Making 1.10 Overhead 0.49 Profit
Order A's FOB price of USD 3.20 is five cost elements added together, not one guessed number. A buyer who sees every line can check each one separately.
What you meet in real life

The shapes a costed quotation takes across export, domestic, MTO and MTS orders

What can differThe shapes you will meetWhy it matters
Export MTO order, established buyerNorthline Apparel receives a full cost breakdown for Order A: fabric 1.15, trims 0.20, making 1.10, overhead 0.49, profit 0.26, FOB 3.20, since the relationship is established and the buyer expects to see the build-up.An established buyer checks the breakdown against past orders, so hiding a cost element damages trust even when the total price is fair.
Export MTO order, new buyerA new export buyer often receives the same five-element breakdown, but with a short note explaining any element that differs from a typical order, since the buyer has no past quotation to compare against.Without past history to check against, a new buyer relies entirely on the breakdown itself to judge whether the price is reasonable.
Domestic MTS order, stock programmeA domestic buyer such as Cedar & Co. buying to stock its own shops often receives a simpler quotation, since the making cost and overhead are close to standard for a repeat stock style, with only fabric and quantity varying between styles.The buyer trusts a simpler quotation faster once a stock programme's own cost pattern is established across several styles.
Hybrid order, mixed quantity commitmentA buyer combining an MTO order with an MTS top-up, such as a trading company reselling to several retailers, often asks for the cost breakdown at two different quantities, to see which cost elements shrink as quantity grows.Only some elements, mainly overhead, fall meaningfully with quantity; fabric and trims per piece barely move, so the buyer needs to see both to judge a volume discount fairly.
The case we follow

Sara checks Delta Garments' quotation for Order A's T-shirt against the specification confirmed in lesson 1.1

Delta Garments sends Northline Apparel a costed quotation for the confirmed specification: 15,000 pieces, 180 GSM single jersey, Ne 30/1 combed cotton, ratio 1:2:2:1. The quotation states fabric USD 1.15, trims USD 0.20, making USD 1.10, overhead USD 0.49, and profit USD 0.26, summing to FOB USD 3.20 per piece. Sara checks the fabric line against the known market fabric price of USD 5.60 per kg and Order A's own fixed 0.205 kg per piece consumption, and finds the two figures agree.

5.60 × 0.205 = USD 1.15 fabric cost per piece, matching the quotation's fabric line
Cost elementQuoted (USD per piece)Sara's check
Fabric1.15Matches 5.60/kg x 0.205 kg
Trims + making + overhead1.79Consistent with a basic single-jersey T-shirt
Profit0.26About 8% of the FOB price, a normal margin

The fabric line checks out exactly, so Sara accepts the quotation as consistent with the specification, rather than accepting the FOB total on trust alone.

The worked number

Building Order A's FOB price from its five cost elements, one line at a time

1.15 + 0.20 = USD 1.35 after fabric and trims
1.35 + 1.10 = USD 2.45 after adding making
2.45 + 0.49 = USD 2.94 after adding overhead
2.94 + 0.26 = USD 3.20, the FOB price written on the quotation
Running total as each cost element is added, USD per piece1.352.452.943.20 FOB
Order A's FOB price of USD 3.20 is built by adding five cost elements, each shown on its own quotation line. Sara can stop and check the total at any step.
The method

Four steps to build, or check, a costed quotation from a confirmed specification

  1. Price the fabric line first, using the confirmed fabric weight and the current market fabric price per kilogram.
  2. Add trims and making, using the specification's own construction detail to judge whether standard rates apply.
  3. Add overhead as a share of running costs, consistent with the factory's usual overhead percentage for this order type.
  4. Add profit last, and state the FOB total as the sum of all five lines, never as a single number with no build-up shown.
The trap

A common mistake is accepting a quotation's total price without checking the fabric line against a known market price

A common mistake is accepting a quotation's total FOB price without checking at least the fabric line against a known market fabric price, since fabric is usually the largest single cost element and the easiest one for a buyer to verify independently. A buyer who skips this check has no way to tell whether an unusually high or low total price comes from a real cost difference or from an error, or a deliberate padding, in one line.

This mistake costs real money when it goes unnoticed. A buyer who accepts an inflated fabric line without checking it against a known market price of USD 5.60 per kg could overpay by several cents per piece across an entire order, a difference that adds up to hundreds of dollars on an order the size of Order A. Checking the one line that is easiest to verify costs Sara a few minutes and protects the rest of the quotation's credibility.

06In plain words

A costed quotation shows a price broken into its parts: fabric, trims, making, overhead and profit, added together to make the final price per piece. A buyer who sees only one total number cannot tell whether the price is fair or what would change if the order changed. A buyer who sees each part can check the biggest and easiest part, usually the fabric cost, against a known market price, and ask about anything that looks wrong. Building or checking a quotation this way, line by line, protects both sides: the factory shows its price is fair, and the buyer knows exactly what it is paying for.

07Quick check
  • A costed quotation shows fabric, trims, making, overhead and profit as separate lines summing to the FOB price.
  • Fabric is usually the largest single cost element and the easiest one to check against a known market price.
  • Overhead falls a little as quantity grows; fabric and trims per piece usually do not.
  • A single total price with no breakdown cannot be checked by the buyer.
  • Always check the fabric line first; it is the fastest way to test whether a quotation is fair.
  • A normal profit margin sits at roughly 5-10% of the FOB price for a standard MTO order.
08Workplace scenario

Northline Apparel's finance team asks Sara to confirm the quotation's FOB price is correct before the purchase order is issued

Delta Garments' quotation states an FOB price of USD 3.20 per piece for the confirmed 15,000-piece, 180 GSM specification. Northline Apparel's finance team asks Sara to confirm the price is correct before the purchase order is issued, since the order is worth USD 48,000.

  • The quotation lists fabric USD 1.15, trims USD 0.20, making USD 1.10, overhead USD 0.49, and profit USD 0.26.
  • The known market fabric price is USD 5.60 per kilogram.
  • Order A's own fixed fabric consumption is 0.205 kg per piece, including marker wastage.
  • Finance needs a clear yes or no before issuing the purchase order.

Can Sara confirm the FOB price is correct from the fabric line alone, or does she need to check every line before answering finance? Decide before opening the answer.

Show decision

Checking the fabric line alone is enough to confirm the quotation is broadly consistent, though not a full guarantee of every line. 5.60 x 0.205 = USD 1.15, exactly matching the quoted fabric line.

First, since fabric is the largest cost element and the easiest to verify independently, a match here is strong evidence the quotation was built honestly rather than padded.

Second, Sara can tell finance the fabric line checks out exactly against the known market price, while noting that trims, making and overhead are harder for a buyer to verify without its own factory-costing knowledge, so the quotation is consistent and reasonable to approve, though not independently proven line by line.

09What it costs

What an unchecked, inflated fabric line could cost Northline Apparel across the whole order

If the fabric line were quietly inflated by USD 0.10 per piece above the correct USD 1.15, the FOB price would read USD 3.30 instead of USD 3.20, with no visible reason for the difference.

3.30 - 3.20 = USD 0.10 overcharge per piece if the fabric line is inflated and unchecked
0.10 × 15,000 = USD 1,500 overpaid across the whole 15,000-piece order

Checking the fabric line against the known USD 5.60-per-kg market price costs Sara only the few minutes it takes to run one calculation, and it protects Northline Apparel from an overpayment of USD 1,500 on this order alone, a sum that recurs on every future order if the same inflated line is accepted without question.

10Working template

Enquiry-to-quotation tracker: recording a quotation's cost elements and Sara's own check against them

Open the course workbook's Quotation Build sheet. For each received quotation, enter the fabric, trims, making, overhead and profit lines, and use the sheet to check the fabric line against the current market fabric price per kilogram.

Download the full working sheet, with Order A's quotation already filled in, from the link on this course's page.

Download the Enquiry-to-quotation tracker (Excel)

11Check yourself

1. What does a costed quotation show that a single total price does not?

2. A quotation for a 4,000-piece order states fabric USD 1.20 per piece. The confirmed fabric weight is 0.20 kg per piece and the market fabric price is USD 6.00 per kg. Is the fabric line consistent?

3. Which cost element in a costed quotation falls the most as order quantity grows, while fabric and trims per piece stay close to fixed?

12Glossary
ENARFRTRMeaning
Costed quotationعرض سعر مفصل التكلفةDevis chiffréMaliyetlendirilmiş teklifA quotation that shows the price broken into its cost elements, not just one total figure, so the buyer can check how it was built.
Cost elementعنصر التكلفةÉlément de coûtMaliyet unsuruOne part of a price, such as fabric, trims, making, overhead, or profit, added together to form the full FOB price.
FOB priceسعر التسليم على ظهر السفينةPrix FOBFOB fiyatıFree on board; the price a buyer pays per piece up to the goods being loaded on the ship, before shipping and duty are added.
Making costتكلفة التصنيعCoût de fabricationİmalat maliyetiThe cost of cutting, sewing and finishing a garment, separate from fabric and trims, one of the five lines in a costed quotation.
Overheadالتكاليف العامةFrais générauxGenel giderlerThe share of a factory's running costs, such as rent, power and salaries, added to each piece's price on top of fabric, trims and making.
MarginالهامشMargeMarjThe profit a factory keeps once every other cost element in the price has been covered.
13Next

Lesson 1.3: Setting a quotation's own validity, MOQ and lead time terms

You now know how a costed quotation is built from a confirmed specification. The next lesson adds the terms that sit around the price: how long it stands, the minimum order quantity, and the lead time. Back to the course map

14Ladder

RecognizeName the five cost elements a costed quotation adds together.
ConnectSee how the fabric line can be checked against a known market price.
CompareTell a costed quotation apart from a single total-price figure.
DecideChoose to check a quotation's most verifiable line before accepting the total.