The same five-component method builds every costing sheet: fabric, trims, making, overhead, profit. That does not mean two orders costed by this method must reach the same total price. Order A's FOB price is USD 3.20; a domestic order for a similar T-shirt can land on a different total entirely, without either sheet being wrong. This lesson shows why: each component's own drivers, a fabric price, a consumption figure, an overhead rate, a chosen margin, can differ from order to order, even when the method that combines them never changes. This lesson mainly teaches the money flow: how the same method can honestly produce two different prices.
You need: the three cost families from the first lesson of this course and the reading method from the second.
By the end of this lesson you can:
Not covered here: common costing mistakes that erase margin (lesson 1.4) and building a costing sheet from a blank page (lesson 1.5).
| Term | Meaning |
|---|---|
| Cost component | One part of a garment's total price: fabric, trims, making, overhead, or profit. |
| Ex-factory price | What the buyer pays the factory for the finished goods, at the factory's own gate, before any delivery cost is added. |
| Delivered cost | The buyer's true cost once the goods have reached its own warehouse: the ex-factory price plus delivery, freight, insurance and duty for an imported order, or local transport for a domestic one. |
| Fabric cost | The cost of the fabric used in one garment, driven by fabric price per kilogram and consumption per piece. |
| Overhead | A factory's running costs that are not fabric, trims or direct labour: rent, electricity, management salaries and similar costs, shared across all the pieces it makes. |
| FOB price | The price the factory charges for the garment, delivered on board the ship at its own port. |
Fabric, trims, making, overhead and profit stack up on every costing sheet, in the same order, for every order a factory ever prices. What differs between two orders is never the method; it is the driver behind each component. One order's fabric may be a finer, more expensive grade than another's, even in the same garment shape. One order's making charge may reflect a factory running near full capacity, spreading overhead thinly, while another's reflects a quieter season. One order's profit margin may be set higher to compensate a factory for a new, less-proven buyer relationship. None of these differences means either costing sheet is wrong; they mean the two orders are genuinely different orders.
| What can differ | The shapes you will meet | Why it matters to you |
|---|---|---|
| Export FOB versus domestic ex-factory framing | Order A's total is an FOB price, since Northline Apparel is an export buyer paying for goods on board the ship. A domestic buyer such as Cedar & Co. pays an ex-factory price instead, then adds its own local delivery cost separately to reach its own delivered cost. | An FOB total and an ex-factory total are not directly comparable numbers; each already excludes a different set of costs the buyer adds afterwards. |
| Fabric grade and price, for the same garment shape | Two T-shirts of the same cut can use different fabric grades, at different prices per kilogram, for reasons of buyer specification, market positioning, or fabric availability, without either garment being a different product. | A lower fabric price does not always mean a lower-quality garment; it may reflect a different, equally valid specification. |
| Order size and overhead absorption | A larger order, like Order A's 15,000 pieces, lets a factory spread its overhead over more pieces, often lowering overhead per piece. A smaller order can carry a higher overhead share per piece for the identical factory and the identical overhead rate. | A smaller order costing more per piece is not evidence of an inefficient factory; it may simply reflect fewer pieces sharing the same fixed cost. |
| Buyer relationship and risk, affecting profit margin | A large, repeat, trusted buyer like Northline Apparel, on Order A, often receives a steadier, sometimes lower, profit margin. A new or smaller buyer relationship can carry a higher margin to compensate the factory for extra risk. | Two otherwise similar orders can carry different profit margins for reasons about the relationship, not the garment. |
Order A's own costing, fixed already in Course 7, sells the T-shirt export FOB at USD 3.20 to Northline Apparel. To show how a domestic sale of a similar T-shirt shape can reach a different total, this lesson uses one clearly labelled illustrative change: a domestic buyer such as Cedar & Co. sourcing the same construction from Delta Garments but at a locally available fabric price of USD 5.20 per kilogram, rather than Order A's own fixed USD 5.60 per kilogram. Every other figure below keeps Order A's own fixed values, so the comparison isolates one driver at a time.
| Component | Order A (export, USD per piece) | Illustrative domestic variant (USD per piece) |
|---|---|---|
| Fabric | 1.15 (5.60/kg x 0.205 kg) | 1.07 (5.20/kg x 0.205 kg, illustrative fabric price) |
| Trims | 0.20 | 0.20 (unchanged) |
| Making | 1.10 | 1.10 (unchanged) |
| Overhead | 0.49 | 0.49 (unchanged) |
| Profit | 0.26 | 0.26 (unchanged) |
| Total | 3.20 (FOB) | 3.12 (ex-factory, illustrative) |
A buyer comparing Order A's USD 3.20 export FOB with a domestic quote of USD 3.12 for what looks like the same T-shirt shape can wrongly conclude the cheaper quote must be cutting corners somewhere. The real explanation can be as simple as a different, locally available fabric price, with every other component identical, as shown in the worked example above. Treating a price gap as automatic proof of a quality gap skips the one step that actually explains anything: asking which driver moved and why.
Every costing sheet uses the same five parts, in the same order: fabric, trims, making, overhead, profit. Two different orders can still end up with two different total prices, and neither sheet is wrong. What actually differs is one or more of the numbers behind a part, not the way the parts are added up. A different fabric price, a different order size, or a different relationship with the buyer can each explain a price gap on their own. A lower price on a similar-looking garment does not automatically mean a worse garment; it might just mean one number behind the price is different for a real, checkable reason.
Omar, the owner of Cedar & Co., is quoted USD 3.12 ex-factory by Delta Garments for a T-shirt of the same construction Order A uses for Northline Apparel, whose own FOB price he has heard is USD 3.20. Omar assumes Delta Garments must be using a cheaper, lower-quality fabric for his order, since his price is lower.
Here is what Omar is comparing:
Does Omar's lower price necessarily mean a lower-quality fabric? Decide before opening the answer.
Not necessarily. Two facts decide this together.
First, what the fabric-price difference alone explains. Fabric at USD 5.20 instead of USD 5.60 per kilogram, with the same 0.205 kilogram consumption, lowers fabric cost by exactly USD 0.08 per piece, which alone would explain the full gap between USD 3.20 and USD 3.12 if every other component stayed the same.
Second, what "cheaper fabric price" does and does not mean. A lower price per kilogram can come from a different, equally suitable fabric source or a locally available grade, not automatically a lower-quality one; fabric price and fabric quality are related but not identical.
Omar's instinct to question a lower price is reasonable. But the right response is to ask Delta Garments what fabric, at what specification, is behind the USD 5.20 figure, not to assume quality has been cut without checking.
Framed qualitatively, if Omar rejects Delta Garments' domestic quote outright, assuming a hidden quality cut, Cedar & Co. may pay more elsewhere for no real benefit, since the fabric-price difference alone already accounts for the gap he saw. A single specification check, comparing both fabrics' own construction and finish, would resolve the question directly.
On an order of a similar size to Order A, that unchecked assumption could cost Cedar & Co. well over a thousand dollars for a quality difference that was never actually verified.
Open the Cost build-up sheet workbook linked below. Its one sheet, "Cost build-up", lists Order A's five components with their own drivers noted. To compare a second order, copy the sheet and change only the driver you believe differs, such as fabric price, leaving every other row at Order A's own value. The resulting total shows exactly how much of the price gap that one driver explains, before you look for any other cause.
[Download the Cost build-up sheet](../../templates/T12-C01-cost-build-up-sheet.xlsx)
1. Why can Order A's export FOB price and Cedar & Co.'s domestic ex-factory price not be compared directly?
2. A large and a small order use the identical factory, fabric price and making charge. Why might the small order show a higher overhead per piece?
3. Two similar garments cost USD 4.00 and USD 4.30, every component identical except making charge, 1.20 higher on the pricier one. What does this reflect?
| EN | AR | FR | TR | Meaning |
|---|---|---|---|---|
| Cost component | عنصر التكلفة | Élément de coût | Maliyet bileşeni | One part of a garment's total price: fabric, trims, making, overhead, or profit. |
| Ex-factory price | سعر خروج المصنع | Prix départ usine | Fabrika çıkış fiyatı | What the buyer pays the factory for the finished goods, at the factory's own gate, before any delivery cost is added. |
| Delivered cost | تكلفة التسليم | Coût rendu | Teslim maliyeti | The buyer's true cost once the goods have reached its own warehouse: the ex-factory price plus delivery, freight, insurance and duty for an imported order, or local transport for a domestic one. |
| Fabric cost | تكلفة القماش | Coût du tissu | Kumaş maliyeti | The cost of the fabric used in one garment, driven by fabric price per kilogram and consumption per piece. |
| Overhead | التكاليف العامة | Frais généraux | Genel giderler | A factory's running costs that are not fabric, trims or direct labour: rent, electricity, management salaries and similar costs, shared across all the pieces it makes. |
| FOB price | سعر التسليم على ظهر السفينة | Prix FOB | FOB fiyatı | The price the factory charges for the garment, delivered on board the ship at its own port. |
You now know why two orders can carry two different total prices even under the same five-component method. The next lesson looks at the mistakes a merchandiser makes when applying that method, and how each one quietly erases margin without anyone noticing at the time. Back to the course map