Course contents
Foundation · Course 1: Understand Garment Cost · Lesson 1 of 5

The main cost categories that build up to a garment's FOB price

Level: FoundationTime: 45 minutesOrder used: A (the T-shirt)Tool: Cost build-up sheet
This lesson is for anyone who wants to understand what sits behind a garment's price, not just its five named parts: a merchandiser, a factory owner, a buyer, or a student. Course 7, lessons 1 and 2 are the prerequisite. This course goes deeper into how each component is calculated. Money figures are teaching examples in US dollars.
BuyerNorthline Apparel (overseas clothing brand)
FactoryDelta Garments (garment factory)
ProductBasic cotton T-shirt, one colour
Quantity15,000 pieces
FOB priceUSD 3.20 per piece
Cost componentsFabric, trims, making, overhead, profit
02Opening

This page explains the three category groups a garment's cost components fall into, for anyone who prices or checks a garment's cost

A garment's price is not just five separate numbers sitting side by side. Course 7 already named the five cost components, fabric, trims, making, overhead and profit, and showed how their shares of price are calculated. This lesson groups those five components into three families, by what actually drives each one, so a merchandiser can tell at a glance which numbers move together and which move on their own. Without this grouping, a person can name all five components and still not know which ones respond to a fabric-price change, which respond to a factory's booking level, and which one is simply a decision. This lesson mainly teaches the money flow: how a price's parts group together by what causes them to change.

03Before you start

What you need, and what this lesson does not cover

You need: the five cost components and the share-of-price formula from Course 7, lessons 1 and 2 (fabric, trims, making, overhead, profit).

By the end of this lesson you can:

  • name the three category groups a garment's cost components fall into: material costs, conversion costs, and profit;
  • explain what drives each category group, in plain words;
  • state which numbers a merchandiser must confirm before trusting a material cost figure;
  • explain why conversion costs move with time and rate, not with a purchase order;
  • tell a driven cost component from one that is a deliberate decision.

Not covered here: how each component's own dollar value is read off a finished sheet (lesson 1.2), why the same garment can cost differently for two orders (lesson 1.3), and common costing mistakes (lesson 1.4).

04Key terms

Words you will meet in this lesson

TermMeaning
Cost componentOne part of a garment's total price: fabric, trims, making, overhead, or profit.
Fabric costThe cost of the fabric used in one garment, driven by fabric price per kilogram and consumption per piece.
Making chargeThe labour cost of cutting, sewing and finishing one garment.
OverheadA factory's running costs that are not fabric, trims or direct labour: rent, electricity, management salaries and similar costs, shared across all the pieces it makes.
TrimsEverything sewn or attached to a garment besides the main fabric: labels, buttons, zips, thread, care labels.
ProfitThe money left over after all costs are paid, out of a selling price.
Share of priceOne cost component's dollar value divided by the total price, usually shown as a percentage.
05Teaching
The rule

A garment's five cost components fall into three families, grouped by what drives them, not by how large they are

Fabric and trims are material costs: money paid to an outside supplier for something the factory bought. Making and overhead are conversion costs: money spent turning those bought materials into a finished garment, through labour time and factory running cost. Profit is its own family: the amount the factory decided to keep, not a pass-through cost at all. Grouping the five components this way matters because each family responds to a different kind of change. A material cost moves when a supplier's price moves or when consumption per piece changes. A conversion cost moves when the garment's construction time changes or when the factory's booking level changes. Profit moves only when the factory chooses to change it.

Order A's material costs: fabric 1.15 + trims 0.20 = 1.35 per piece
Order A's conversion costs: making 1.10 + overhead 0.49 = 1.59 per piece
Order A's profit: 0.26 per piece
What you meet in real life

The same three families appear on every order, but which family dominates changes with the product and the factory

What can differThe shapes you will meetWhy it matters to you
Which family is largestOn a simple, fabric-heavy style like Order A's T-shirt, material costs (fabric and trims combined) are close to conversion costs. On a construction-heavy style, such as a lined jacket, conversion costs usually dominate.Knowing which family dominates tells you where a price change is most likely to come from next.
Export or domestic pricingOrder A's costing is framed as an FOB export price, all five components priced the same way. Cedar & Co.'s own domestic costing keeps the same three families, but its total is an ex-factory price, with local delivery added on top rather than export freight.The three families do not change between export and domestic business; only the price they are compared against changes.
Make-to-order versus make-to-stockOrder A is a make-to-order export order: Delta Garments prices it once, against Northline Apparel's own specification and quantity. Cedar & Co. buys on a make-to-stock basis, forecasting its own demand, so the same three families are priced against a style Cedar & Co. itself designed.Who sets the specification changes who controls each cost driver, but not which family a cost belongs to.
How exposed each family is to currency and commodity swingsMaterial costs (fabric, trims) are the family most exposed to a raw-material price swing, since fabric is usually bought in the same currency the mill quotes in. Conversion costs move more slowly, since a factory's labour rate and overhead rate change less often than a fabric price.A merchandiser who tracks fabric-market news is really watching one family, not the whole price.
The case we follow

Delta Garments' merchandiser groups Order A's five components into the three families before quoting Northline Apparel

Mona, the merchandiser at Delta Garments, is preparing to discuss Order A's costing with Sara at Northline Apparel. Before the call, she groups the five already-fixed components into their three families, so she can answer questions about which numbers might change and which will not.

FamilyComponentsOrder A (USD per piece)Share of price
Material costsFabric + trims1.15 + 0.20 = 1.3542.1875%
Conversion costsMaking + overhead1.10 + 0.49 = 1.5949.6875%
ProfitProfit0.268.125%
Total (FOB price)3.20100%
The worked number

Conversion costs are the largest family on Order A, just ahead of material costs

Material costs' share: (1.15 + 0.20) / 3.20 = 1.35 / 3.20 = 0.421875, about 42.2%
Conversion costs' share: (1.10 + 0.49) / 3.20 = 1.59 / 3.20 = 0.496875, about 49.7%
Profit's share: 0.26 / 3.20 = 0.08125, about 8.1%
Order A: FOB price USD 3.20 per piece, by familyMaterial costs 1.35Conversion costs 1.59Profit 0.26
Order A's price splits almost evenly between material and conversion costs, with profit the smallest family. Conversion costs (making and overhead together) edge ahead of material costs (fabric and trims together) on this style.
The method

Group any garment's cost components into their three families in four steps

  1. List the garment's five cost components from its costing sheet: fabric, trims, making, overhead, profit.
  2. Sort fabric and trims into material costs, making and overhead into conversion costs, and leave profit on its own.
  3. Sum each family's dollar value and divide by the total price to get the family's share.
  4. Ask, for each family, what would make it change: a supplier price, a construction time, a booking level, or a decision.
The trap

A common mistake is treating overhead as a material cost because it is quoted as a single dollar figure like fabric

Overhead is quoted on a costing sheet the same way fabric is, as one dollar figure per piece, and this can lead a new merchandiser to treat the two the same way when looking for a saving. Fabric is a material cost: it can be reduced by negotiating a lower price per kilogram or a lower consumption per piece, both specific to this order. Overhead is a conversion cost: it is the factory's own running cost, absorbed across every order it makes, and cannot be renegotiated order by order the way a fabric price can. Confusing the two families sends a merchandiser to negotiate a number that the factory itself cannot move for one order alone.

Fabric (material cost)Overhead (conversion cost)Bought fresh for this orderfrom Colorline Dyeing.Price per kilogram can berenegotiated for Order A alone.Shared across every orderDelta Garments runs.Cannot be cut for Order Aalone without a factory-wide change.
Fabric and overhead can look alike on a costing sheet but behave differently. Fabric responds to a single order's own negotiation; overhead responds only to a change across the whole factory.
06In plain words

A garment's price has five parts, and those five parts fall into three groups. Fabric and trims are things the factory bought, so they are called material costs. Making and overhead are the cost of turning those bought things into a finished garment, so they are called conversion costs. Profit is what the factory decided to keep, on its own. Knowing which group a cost belongs to tells you what would actually make that cost change: material costs change when a supplier's price or the amount used per piece changes; conversion costs change when the work takes more or less time, or when the factory has more or fewer orders to spread its running cost across; profit changes only when the factory decides to change it.

07Quick check
  • Fabric and trims are material costs: money paid to an outside supplier for something bought.
  • Making and overhead are conversion costs: money spent turning bought materials into a finished garment.
  • Profit is its own family: a deliberate decision, not a pass-through cost at all.
  • A material cost moves when a supplier's price or a consumption figure changes.
  • A conversion cost moves when construction time changes or a factory's booking level changes.
  • The same three families apply whether the order is export or domestic, MTO or MTS.
  • A cost component's size does not tell you how easily it can be moved for one order.
08Workplace scenario

A new merchandiser at Delta Garments proposes negotiating overhead down the same way as fabric to protect Order A's margin

A new merchandiser joins Delta Garments and reviews Order A's costing sheet. Seeing fabric at USD 1.15 and overhead at USD 0.49, both quoted as single dollar figures, they suggest to Mona that the same negotiation approach used on fabric, asking the supplier for a lower price, should also be tried on overhead, to protect Order A's margin.

Here is the costing sheet they are looking at:

Order A costing sheet (per piece, USD). Fabric 1.15. Trims 0.20. Making 1.10. Overhead 0.49. Profit 0.26. Total FOB price 3.20.

Can overhead be negotiated down for Order A the same way fabric can? Decide before opening the answer.

Show decision

No, not in the same way. Two facts decide this together.

First, what fabric actually is. Fabric is a material cost: Delta Garments buys it fresh from Colorline Dyeing for this order, and its price per kilogram is a live negotiation between two named companies, specific to Order A.

Second, what overhead actually is. Overhead is a conversion cost: it is Delta Garments' own rent, electricity and management cost, already spread across every order the factory runs this year. There is no outside supplier to negotiate with, and cutting it for Order A alone would mean changing how the whole factory absorbs its running cost, a decision far bigger than one order's merchandiser can make.

The new merchandiser's instinct, that a bigger-looking number deserves attention, is reasonable. But fabric and overhead belong to different families, and only material costs like fabric can be moved by a single order's own negotiation.

09What it costs

Chasing the wrong family wastes a merchandiser's negotiating time on a number that will not move

Framed qualitatively, time spent trying to negotiate overhead down for one order is time not spent on the family that can actually move: material costs. If Mona's new colleague spends a week preparing an overhead-reduction pitch instead of following up with Colorline Dyeing on a fabric-price discount, that week produces no saving, since overhead is fixed factory-wide regardless of Order A's own outcome. A one-percentage-point drop in fabric price, by contrast, is a real, order-specific saving.

A 1 percentage-point fabric-price drop: 1.15 x 0.01 = 0.0115 saved per piece, on 15,000 pieces = USD 172.50 saved on Order A

Chasing overhead instead of fabric on this order risks losing a realistic saving of over USD 170 for no result at all.

10Working template

Cost build-up sheet: read Order A's own grouped rows, then work out your own order's family shares

Open the Cost build-up sheet workbook linked below. Its one sheet, "Cost build-up", lists Order A's five components, each with a note on how the amount is driven, its own dollar value, and a share-of-price column calculated by formula, never typed in. Fabric's row shows the calculation behind its 1.15 figure; the other four rows are typed values, since no further fixed driver figures exist for them at the academy. Group the five rows yourself into material costs, conversion costs and profit, then fill in the yellow "Your order" column with your own five numbers.

[Download the Cost build-up sheet](../../templates/T12-C01-cost-build-up-sheet.xlsx)

Download the Cost build-up sheet (Excel)

11Check yourself

1. Which two cost components are material costs, paid to an outside supplier?

2. Why can overhead not be negotiated down for one order the way fabric can?

3. A different order has making USD 1.80, overhead USD 0.65, fabric USD 2.10 and trims USD 0.45, on a total price of USD 5.60. What is that order's conversion-cost share of price?

12Glossary
ENARFRTRMeaning
Cost componentعنصر التكلفةÉlément de coûtMaliyet bileşeniOne part of a garment's total price: fabric, trims, making, overhead, or profit.
Fabric costتكلفة القماشCoût du tissuKumaş maliyetiThe cost of the fabric used in one garment, driven by fabric price per kilogram and consumption per piece.
Making chargeتكلفة التصنيعCoût de façonİşçilik (fason) maliyetiThe labour cost of cutting, sewing and finishing one garment.
Overheadالتكاليف العامةFrais générauxGenel giderlerA factory's running costs that are not fabric, trims or direct labour: rent, electricity, management salaries and similar costs, shared across all the pieces it makes.
TrimsالإكسسواراتFournitures (accessoires)Aksesuar (yardımcı malzeme)Everything sewn or attached to a garment besides the main fabric: labels, buttons, zips, thread, care labels.
ProfitالربحProfitKârThe money left over after all costs are paid, out of a selling price.
Share of priceنسبة السعرPart du prixFiyat payıOne cost component's dollar value divided by the total price, usually shown as a percentage.
13Next

Lesson 1.2: Reading a finished costing sheet from fabric to final FOB

You now know the three category groups a garment's five cost components fall into, and why each group is driven differently. The next lesson reads a finished costing sheet line by line and shows exactly which numbers feed each component's own dollar value. Back to the course map

14Ladder

RecognizeName the three families a garment's five cost components fall into.
ConnectSee why each family responds to a different kind of change.
CompareTell a material cost like fabric from a conversion cost like overhead, despite both looking like a single dollar figure.
DecideJudge which family a realistic saving is likely to come from on a given order.