Practitioner · Course 2: Range and Assortment Planning · Lesson 4 of 5

Phasing a range's own delivery across a selling season

Level: PractitionerTime: 45 minutesOrder used: A (the T-shirt) and B (the denim style), phased across two delivery dropsTool: Range and assortment plan workbook
This lesson is for an agent, buyer or factory coordinating a range's own delivery phasing across a season. Lesson 2.3 is useful background but not required. Fairway Stores' delivery-drop split is an illustrative teaching example, not reported company data.
AgentMeridian Sourcing, coordinating Fairway Stores' range with two factories
BuyerFairway Stores' buyer
Order A's own scheduleT-shirt, ready for shipment on its own fixed schedule
Fairway Stores' illustrative delivery splitDrop 1: T-shirt basics; Drop 2 later: the denim style
Order B's own scheduleDenim style, ready after its own fixed washing stage
What this lesson setsThe delivery week for each style, not just its factory-ready date
02Opening

This page explains why a range's styles are phased into separate delivery drops across a season instead of all arriving on one date

This page explains delivery phasing: deciding which week of a selling season each style in a range should reach the shop, rather than shipping every style on the same date regardless of its own production timeline or its role in the season. It is for an agent, buyer or factory that coordinates a multi-style range across more than one production schedule.

At work, an agent such as Meridian Sourcing coordinates styles from different factories, or with different production timelines, that are meant to sell across the same season. Order A's T-shirt has a much shorter production schedule than Order B's jeans, which need extra time for washing. Treating every style as if it must arrive on the same single date is a real problem: it either delays the faster style unnecessarily to match the slower one, or forces the slower style's own schedule to be compressed at extra cost. This lesson gives you the method for phasing delivery so each style reaches the shop at the week that actually suits both its own production schedule and its role in the season.

03Before you start

What you need, and what this lesson does not cover

You need: lesson 2.3's quantity breakdown by colour and size is useful background but not required.

By the end of this lesson you can:

  • state why a range's styles are phased into separate delivery drops rather than arriving on one date;
  • compare Order A's own 16-week schedule against Order B's jeans' own 22-week schedule and say what that gap means for phasing;
  • apply the method for assigning each style a delivery drop based on its production timeline and its role in the season;
  • read the range and assortment plan workbook's delivery-drop column and say what it adds to a quantified range;
  • avoid the common mistake of compressing a slower style's timeline just to match a faster style's delivery date.

Not covered here: assembling a complete range and assortment plan that brings range building, classification, quantities and phasing together (lesson 2.5).

04Key terms

Words you will meet in this lesson

TermMeaning
Delivery dropA scheduled point in a season when one or more styles from a range are delivered to the shop together.
PhasingSpreading a range's styles across more than one delivery drop, timed to each style's own production schedule and role in the season.
Production timelineThe full sequence of production steps a style must complete, from order placement to being ready for shipment.
Sell-through windowThe period a style is expected to be actively sold before it is replaced, discounted or withdrawn.
Critical pathThe sequence of production steps that sets a style's own earliest possible delivery date.
Consolidated shipmentCombining more than one style into a single shipment once both are ready, rather than shipping each the moment it is individually finished.
05Teaching
The rule

A range's styles are phased into delivery drops timed to each style's own production timeline, not forced onto one shared date

Every style in a range has its own critical path, the sequence of production steps that sets its own earliest possible delivery date. A range with styles on different critical paths cannot deliver all of them on the same date without either delaying the faster style or compressing the slower one. Phasing solves this: it spreads a range's styles across more than one delivery drop, each timed to the styles that are actually ready for it, so a range reaches the shop across the season rather than all at once.

Order A16 weeks → Drop 1 Order B jeans22 weeks → Drop 2 One range,phased across the season
Two different critical paths lead to two delivery drops, not one shared date. Phasing lets each style arrive when its own timeline, and the season, actually calls for it.
What you meet in real life

Phasing decisions differ by market, model and who is coordinating them, but every multi-style range needs a phasing plan

What can differThe shapes you will meetWhy it matters
Export, hybrid coordinationMeridian Sourcing phases Fairway Stores' range across Order A's 16-week and Order B's jeans' 22-week schedules from two different production paths, agreeing drop dates with both factories.An agent sitting between buyer and factories must reconcile more than one critical path into one season plan.
Domestic, make to stockCedar & Co. phases a basic T-shirt reorder as a continuous drop, replenished as stock runs low, against a seasonal print style delivered once at a single planned drop.Make-to-stock phasing can mix a continuous drop with a one-off seasonal drop in the same range.
Styles on the same critical pathTwo styles made by the same factory, in the same fabric, with near-identical production steps, can share one delivery drop without any compression needed.Not every range needs multiple drops; phasing matches drops to real differences in timeline, not to style count alone.
A style needed early for marketingA style with a longer production timeline but an early planned launch date may need its own critical path started earlier than a shorter-timeline style planned for later in the season.Phasing considers a style's planned selling window, not only how fast it can be produced.
The case we follow

Meridian Sourcing phases Fairway Stores' range into two drops, Order A's T-shirt six weeks ahead of Order B's jeans

Meridian Sourcing, the agent coordinating Fairway Stores' range across two factory timelines, phases the range into two delivery drops. Drop 1 carries Order A's T-shirts, ready at week 16. Drop 2 carries Order B's jeans, ready at week 22, six weeks later. Rather than delaying the T-shirts to wait for the jeans, or rushing the jeans' washing stage to catch up, Meridian Sourcing schedules two separate drops, each timed to its own style's real critical path.

QuestionForcing one shared delivery datePhasing into two drops
What happens to Order A's T-shirt?Held back six weeks past its own 16-week readiness, for no production reasonDelivered at week 16, as soon as it is genuinely ready
What happens to Order B's jeans?Compressed, risking a rushed wash stage or added cost to catch upDelivered at week 22, on its own real critical path
Who has to manage the mismatch?Fairway Stores, receiving a delayed or a rushed, higher-risk shipmentMeridian Sourcing, coordinating two clean, on-time drops instead
The worked number

Order B's jeans reach the shop 6 weeks after Order A's T-shirt, the exact gap between their two fixed timelines

Order A's own fixed timeline is 16 weeks; Order B's jeans' own fixed timeline is 22 weeks. The gap between the two sets the phasing interval between Drop 1 and Drop 2.

Order B's own jeans timeline: 22 weeks
Order A's own timeline: 16 weeks
Gap between the two drops: 22 − 16 = 6 weeks
Drop 1: week 16 Drop 2: week 22 6-week phasing gap
The 6-week gap between drops is not a scheduling choice; it is the fixed difference between Order A's own 16-week and Order B's jeans' own 22-week schedules. Phasing simply reflects that real gap rather than hiding it.
The method

Four steps that assign each style in a range to a delivery drop, timed correctly across a selling season

  1. Confirm each style's own critical path and its real earliest-ready date. Use each style's own fixed timeline, such as Order A's 16 weeks or Order B's jeans' 22 weeks, not an assumed shared date.
  2. Group styles with genuinely similar ready dates into the same drop. Styles ready within the same short window can share one delivery drop without compression.
  3. Separate styles with a real gap between them into distinct drops. A gap as large as Order A and Order B's jeans' own 6 weeks calls for two drops, not one compressed or delayed date.
  4. Confirm each drop's date against the season's own selling calendar. A style should also reach the shop within its planned selling window, not only as soon as production allows.
The trap

A common mistake is forcing every style in a range onto one shared delivery date regardless of each style's own critical path

A common mistake is picking a single delivery date for a whole range and working backward, forcing every style's production to fit it, rather than phasing drops around each style's own real timeline. If Meridian Sourcing had forced Order B's jeans to ship alongside Order A's T-shirt at week 16, six weeks before the jeans' own washing stage could genuinely finish, the jeans would either arrive with incomplete washing or require rushed, higher-cost production to compress six weeks out of a critical path that does not actually compress that far without quality risk.

06In plain words

A range's styles do not all need to arrive in shops on the same date. Each style has its own production timeline, and phasing spreads a range's delivery across the season to match those real timelines, rather than forcing every style to wait for the slowest one or rushing the slowest one to catch the fastest. Styles with genuinely similar ready dates can share one delivery drop; styles with a real gap between them, like Order A's 16 weeks and Order B's jeans' 22 weeks, need separate drops instead. A drop's timing should also fit the season's own selling calendar, not just a factory's own readiness date.

07Quick check
  • A range's styles are phased into delivery drops timed to each style's own critical path, not forced onto one shared date.
  • The gap between Order A's own 16-week and Order B's jeans' own 22-week schedules is exactly 6 weeks, and that gap sets the phasing interval between their drops.
  • Styles with genuinely similar ready dates can share a drop; styles with a real gap need separate ones.
  • A drop's date should also fit the season's own selling calendar, not only a factory's readiness date.
  • Compressing a slower style's timeline to match a faster style's delivery date trades real production time for cost and quality risk.
08Workplace scenario

Fairway Stores' buyer asks Meridian Sourcing whether Order B's jeans can ship alongside Order A's T-shirt at week 16 instead of week 22

Fairway Stores' buyer wants both styles in shops for the same marketing launch date and asks Meridian Sourcing whether Order B's jeans, on its own 22-week schedule, can be compressed to ship at week 16 alongside Order A's T-shirt.

  • Order B's jeans' own fixed timeline includes 3 weeks of washing that only begins once sewing is complete.
  • Compressing 6 weeks out of a 22-week schedule would fall inside the washing and finishing stages, not an easily shortened stage such as approvals.
  • Order A's T-shirt is already on track for its own genuine week-16 readiness.

Meridian Sourcing's note to Fairway Stores' buyer:

Meridian Sourcing: "Order B's jeans' own washing stage alone needs 3 weeks after sewing finishes. Compressing 6 weeks out of its 22-week schedule risks incomplete washing or a rushed finish. Could Drop 2 launch 6 weeks after Drop 1 instead?"

Should Order B's jeans be compressed to ship alongside Order A's T-shirt at week 16? Decide before you open the answer.

Show decision

No. A shared marketing date is a scheduling preference, not a production reality, and Order B's jeans' own critical path does not have 6 weeks of slack to give up without risk.

First, where the 6 weeks would have to come from. Order B's jeans' washing stage takes 3 of its 22 weeks and cannot start before sewing finishes; compressing the timeline would cut directly into washing or finishing, the stages most likely to affect quality.

Second, what compressing that far actually risks. Rushing washing and finishing risks jeans reaching Fairway Stores with an incomplete wash or finish, a quality problem that a shared launch date does not justify.

Meridian Sourcing should hold Order B's jeans to its own 22-week schedule and phase Drop 2 six weeks after Drop 1, proposing a launch approach that uses two drops rather than one shared date. Lesson 2.5 develops how these phased drops fit into a complete range and assortment plan.

09What it costs

Compressing Order B's jeans' own 22-week schedule by 6 weeks to match Order A's delivery date risks a rushed wash stage or added cost

Framed in time and risk rather than a single penalty figure: forcing a shared week-16 delivery date would require removing 6 weeks from a 22-week schedule that includes a fixed 3-week washing stage.

Order B's own full jeans timeline: 22 weeks
Weeks that would need to be removed for a shared week-16 date: 22 − 16 = 6 weeks
Order B's own fixed jeans washing stage: 3 weeks

Since the washing stage alone accounts for 3 of the 22 weeks and cannot begin before sewing finishes, removing 6 weeks unavoidably cuts into washing, finishing, or both. The realistic alternatives are a quality risk from incomplete washing, or extra cost from expedited processing, neither of which a shared marketing date is worth risking when a six-week-later Drop 2 avoids both entirely.

10Working template

Range and assortment plan workbook: the delivery-drop column this lesson fills

The workbook's "Phasing" sheet lists each style alongside its own critical-path timeline, its earliest-ready week, and an assigned delivery-drop number, with a check that flags any style assigned to a drop earlier than its own real readiness date.

Meridian Sourcing's own rows record Order A's T-shirt at week 16 in Drop 1, and Order B's jeans at week 22 in Drop 2, with the sheet's built-in check confirming neither style is scheduled ahead of its own genuine critical path.

Download the Range and assortment plan workbook (Excel)

11Check yourself

1. Why does a range with styles on different critical paths need more than one delivery drop?

2. Order A's T-shirt is ready at week 16 and Order B's jeans are ready at week 22. What does this mean for phasing their delivery?

3. Fairway Stores' buyer wants Order B's jeans to ship with Order A's T-shirt at week 16 for a shared launch. What should Meridian Sourcing recommend?

12Glossary
ENARFRTRMeaning
Delivery dropدفعة تسليمLivraison échelonnéeTeslimat partisiA scheduled point in a season when one or more styles from a range are delivered to the shop together.
Phasingالتوزيع على مراحلPhasageAşamalandırmaSpreading a range's styles across more than one delivery drop, timed to each style's own production schedule and role in the season.
Production timelineالجدول الزمني للإنتاجCalendrier de productionÜretim zaman çizelgesiThe full sequence of production steps a style must complete, from order placement to being ready for shipment.
Sell-through windowنافذة البيعFenêtre de venteSatış penceresiThe period a style is expected to be actively sold before it is replaced, discounted or withdrawn.
Critical pathالمسار الحرجChemin critiqueKritik yolThe sequence of production steps that sets a style's own earliest possible delivery date.
Consolidated shipmentشحنة موحّدةExpédition groupéeKonsolide sevkiyatCombining more than one style into a single shipment once both are ready, rather than shipping each the moment it is individually finished.
13Next

Lesson 2.5: Building a complete range and assortment plan

You now know how to phase a range's delivery across a season. The final lesson brings range building, classification, quantity splitting and phasing together into one complete range and assortment plan. Back to the course map

14Ladder

RecognizeTell a genuinely shared delivery drop apart from two styles forced onto one date despite different timelines.
ConnectSee how the gap between Order A's and Order B's jeans' own fixed timelines sets the phasing interval between drops.
CompareTell an agent's phasing view across two factories from a domestic buyer's own continuous-versus-seasonal phasing.
DecideHold a style to its own real critical path rather than compressing it to match another style's delivery date.