Course contents
Practitioner · Course 3: Material Requirement Planning · Lesson 2 of 5

Calculating material requirements across several orders sharing the same fabric

Level: PractitionerTime: 45 minutesOrder used: A (the T-shirt), plus an illustrative domestic orderTool: Material requirement planner
This lesson reuses Order A's own fixed fabric figures and adds one illustrative second order, a domestic run for Cedar & Co. using a similar fabric, to teach how two orders sharing a fabric are combined. The illustrative order is not a new fixed academy fact.
FactoryDelta Garments (garment factory)
Order A fabric0.205 kg per piece, 15,000 pieces, single jersey 180 GSM
Order A total3,075 kg
Illustrative second orderCedar & Co., single jersey 180 GSM, 0.18 kg per piece, 6,000 pieces
Illustrative second order total1,080 kg (illustrative)
Combined fabric requirement4,155 kg (illustrative, Order A plus the illustrative order)
02Opening

This page teaches a merchandiser or planner how to combine two or more orders' material requirements when they share the same fabric, so the mill receives one combined purchase order rather than two separate ones. It is for anyone planning purchasing across more than one order at once, building on Lesson 13.3.1's line-by-line method. It mainly teaches the information flow: turning two orders' bills of materials into one combined requirement.

At work, a factory rarely runs one order at a time. Delta Garments produces Order A for Northline Apparel, an export run, while also producing domestic runs for a local brand such as Cedar & Co., and more than one order can use the same or a similar fabric from the same mill. Ordering that fabric twice, without checking the other order, risks missing a shared mill discount or a dye-lot mismatch.

Order A's own fabric figure is already fixed at 0.205 kg per piece for 15,000 pieces. This lesson pairs it, for teaching purposes only, with an illustrative domestic order using a similar fabric, to show how two orders' requirements are added into one combined figure without double-counting either order.

03Before you start

You need: Lesson 13.3.1's line-by-line method for turning a bill of materials into a material requirement list.

By the end of this lesson you can:

  • State why two orders sharing the same fabric are planned together rather than ordered separately.
  • Calculate each order's own material requirement before combining them.
  • Add two orders' fabric requirements into one combined total for a shared purchase order.
  • Recognise when two orders' fabrics are similar but not identical, and why that still matters to a mill.
  • Use this course's material requirement planner to combine more than one order's requirement with live formulas.

Not covered here: building one order's own material requirement list from its bill of materials (Lesson 13.3.1), adding lead time and safety stock to a combined requirement (Lesson 13.3.3), spotting a shortfall against a combined requirement (Lesson 13.3.4).

04Key terms
TermMeaning
Bill of materialsThe list of every material and cost component in a garment, with its cost, used to build up the FOB price.
Total fabric requirementThe full quantity of fabric an order needs, calculated from per-piece consumption times order quantity.
Fabric consumptionThe amount of fabric (by weight or length) one garment piece uses, the basis for calculating an order's total fabric requirement.
Make to Order (MTO)Production starts only after a specific buyer has confirmed a specific order, with quantity, price and delivery date agreed.
05Teaching
The rule

Two or more orders sharing the same fabric are combined into one material requirement before a purchase order is released to the mill.

When more than one order draws on the same fabric, or a fabric close enough in construction and weight that one mill can produce both, each order's own total fabric requirement is calculated first, on its own order quantity, then the two totals are added together into one combined figure. The combined figure is what goes to the mill as a single purchase order, rather than two separate ones. Order A's own 3,075 kg stays exactly as fixed; only the combining step is new.

OrderFabric requirementOrder A, 0.205 kg x 15,000 pieces3,075 kgIllustrative Cedar & Co. order, 0.18 kg x 6,000 pieces1,080 kg (illustrative)Combined purchase order to the mill4,155 kg (illustrative)
Each order keeps its own total before the two are added. Order A's fixed 3,075 kg and an illustrative 1,080 kg order combine into one 4,155 kg figure for a single purchase order.
What you meet in real life

Two orders sharing a fabric can differ in how similar that fabric actually is, and in whether both orders' quantities are already fixed.

What can differThe shapes you meetWhy it matters
Identical fabric, two export ordersTwo Make to Order export orders both confirmed against the same specification, same GSM, same constructionTheir requirements add together directly, with no adjustment needed before combining
Similar but not identical fabricAn export order's single jersey at 180 GSM and a domestic order's single jersey at a different GSM, same mill, same fibreA mill may still combine both into one dyeing lot, but the two fabrics are never treated as literally the same fabric when checking quality or shade
Export MTO paired with domestic MTSOrder A's confirmed 15,000-piece export quantity paired with a domestic brand's forecast-based quantityThe export figure is fixed once confirmed; the domestic figure can move if the forecast changes, so the combined total may need revisiting
One order's quantity changes after combiningA domestic brand revises its forecast downward after a combined purchase order has already gone to the millThe combined figure, not just the one order that changed, must be corrected before the mill's production run is affected
Related product familiesSocks and hosiery mills combining more than one brand's yarn order into one dye lot, home-textile converters combining more than one bedding order's sheeting fabricThe same combining logic applies wherever more than one order can share a mill's production run
The case we follow

Delta Garments combines Order A's fabric requirement with an illustrative domestic order's requirement before ordering from Rowad Knits.

Delta Garments produces Order A for Northline Apparel and, illustratively for this lesson, a second domestic order for Cedar & Co. using a similar single-jersey fabric from the same mill, Rowad Knits. Rather than sending Rowad Knits two separate purchase orders in the same week, Delta Garments' planner combines both orders' fabric requirements into one purchase order, letting Rowad Knits plan one knitting and dyeing run instead of two.

Combining the two purchase orders also helps Delta Garments itself. A single, larger purchase order can qualify for a better fabric price per kilogram than two smaller ones placed separately, and Rowad Knits can offer Delta Garments a more reliable delivery date once it knows the full quantity it must plan capacity for in one run, rather than guessing whether a second, smaller order might still arrive later in the same week and disrupt its schedule.

The worked number

Order A's 3,075 kg combined with an illustrative domestic order's 1,080 kg gives one 4,155 kg purchase order.

Order A's own fixed figures: 0.205 kg per piece multiplied by 15,000 pieces.

0.205 × 15,000 = 3,075

The illustrative domestic order's figures, for teaching purposes only: 0.18 kg per piece multiplied by 6,000 pieces.

0.18 × 6,000 = 1,080

The two orders' fabric requirements added together:

3,075 + 1,080 = 4,155

Delta Garments' planner releases one combined purchase order to Rowad Knits for 4,155 kg, rather than two separate ones, worked out live on this course's material requirement planner.

Two separate purchase orders3,075 kg + 1,080 kgTwo production runs at the millOne combined purchase order4,155 kgOne production run at the mill
Combining two orders' requirements produces one purchase order instead of two. Order A's fixed 3,075 kg and an illustrative 1,080 kg order add to 4,155 kg for a single run at Rowad Knits.
The method

Follow four steps to combine two or more orders' requirements for a shared fabric.

  1. Calculate each order's own total fabric requirement separately, on its own order quantity, exactly as in Lesson 13.3.1.
  2. Confirm the fabrics are the same or close enough in construction and weight that one mill can supply both from one purchase order.
  3. Add each order's own total together into one combined figure.
  4. Track which part of the combined total belongs to which order, so a change to one order's quantity can still be corrected without recalculating the whole combined figure from scratch.
The trap

A common mistake is combining two orders' fabric requirements without first confirming the fabrics are actually close enough to share one purchase order.

A common mistake is adding two orders' fabric weights together because both use "single jersey" fabric, without checking that their GSM, fibre content or finish are close enough for one mill run and one dye lot to serve both. Two single-jersey fabrics at different GSM are not interchangeable at the cutting table even if their weights can be added on paper. Combining them into one purchase order without checking this first can deliver a mill's finished fabric that fits neither order's own specification exactly, and correcting a wrongly combined order after fabric has already been knitted and dyed costs far more time than checking the two specifications side by side before the purchase order is ever sent.

06In plain words

This lesson shows what to do when two different orders both need the same, or a very similar, kind of fabric from the same mill. Instead of asking the mill for fabric twice, in two separate small requests, the two orders' amounts are added together into one bigger request. This lets the mill do one production run instead of two, which is usually easier for the mill and faster for both orders. Before adding the two amounts together, it always has to be checked that the two fabrics really are close enough to be treated as one order at the mill.

07Quick check
  • Combined fabric requirement = each order's own total fabric requirement, added together.
  • Each order's own total is calculated first, on its own order quantity, before the two are combined.
  • Two fabrics must be close enough in construction and weight before their requirements are combined into one purchase order.
  • A Make to Order quantity is fixed once confirmed; a Make to Stock quantity paired with it can still move.
  • If one order's quantity changes after combining, the combined total is corrected, not just the order that changed.
  • Never assume two fabrics are interchangeable just because both weights can be added together on paper.
08Workplace scenario

Mona, the merchandiser at Delta Garments, is preparing purchase orders for the same week. Order A, for Northline Apparel, needs 3,075 kg of single-jersey fabric. An illustrative domestic order for Cedar & Co., using a similar single-jersey fabric from the same mill, needs 1,080 kg.

  • Order A's confirmed fabric requirement is 3,075 kg, 0.205 kg per piece for 15,000 pieces.
  • The illustrative domestic order's fabric requirement is 1,080 kg, 0.18 kg per piece for 6,000 pieces.
  • Both fabrics are single jersey from Rowad Knits, close enough in construction for one dyeing lot.
Rowad Knits' own minimum-run note. "A combined purchase order of this size lets us schedule one knitting and dyeing run instead of two separate smaller runs."

Should Mona send Rowad Knits two separate purchase orders, or one combined purchase order?

Show decision

Mona should send Rowad Knits one combined purchase order for 4,155 kg, from Order A's 3,075 kg plus the illustrative domestic order's 1,080 kg, since both fabrics are single jersey close enough in construction and weight for one mill run. Sending two separate purchase orders in the same week for closely related fabric would ask Rowad Knits to schedule two smaller runs instead of one, which is less efficient for the mill and can push both orders' fabric further down its production queue.

09What it costs

Combining two orders' requirements into one purchase order, rather than sending two separate ones, does not change the total fabric ordered, 4,155 kg either way, but it changes how efficiently the mill can produce it. A mill scheduling two smaller runs instead of one combined run for closely related fabric can take longer overall, since each run carries its own setup time regardless of size.

3,075 + 1,080 = 4,155

The combined fabric requirement, in kilograms, that a single purchase order asks Rowad Knits to produce in one run rather than two.

If Mona had sent two separate purchase orders instead, both orders could face a longer wait for their fabric, since Rowad Knits' knitting and dyeing capacity would be split across two smaller, separately-scheduled runs rather than one combined run, risking a delay to Order A's own fixed 16-week production schedule that a combined purchase order avoids.

10Working template

The Material requirement planner (this course's workbook) holds the "Combine Orders" sheet, which reads each order's own fabric requirement and combines any two or more rows sharing the same fabric into one total, automatically, as a live formula.

QuestionOrder A (filled in)Illustrative domestic order (filled in)Your combined figure
Fabric typeSingle jersey, 180 GSMSingle jersey, similar GSM
Consumption per piece0.205 kg0.18 kg
Order quantity15,000 pieces6,000 pieces
Own total requirement3,075 kg1,080 kg
Combined requirement4,155 kg

Download the Material requirement planner from the course page and combine your own orders' figures in the fourth column.

Download the Material requirement planner (Excel)

11Check yourself

1. Why are two orders' fabric requirements combined into one purchase order instead of sent to the mill separately?

2. Order A needs 3,075 kg of fabric and an illustrative second order needs 1,080 kg of a similar fabric from the same mill. What is the combined purchase order quantity?

3. A domestic order's forecast is revised downward after its fabric requirement was already combined into one purchase order with an export order. What should happen next?

12Glossary
ENARFRTRMeaning
Bill of materialsقائمة الموادNomenclatureMalzeme listesiThe list of every material and cost component in a garment, with its cost, used to build up the FOB price.
Total fabric requirementإجمالي احتياج القماشBesoin total en tissuToplam kumaş ihtiyacıThe full quantity of fabric an order needs, calculated from per-piece consumption times order quantity.
Fabric consumptionاستهلاك القماشConsommation de tissuKumaş tüketimiThe amount of fabric (by weight or length) one garment piece uses, the basis for calculating an order's total fabric requirement.
Make to Order (MTO)الإنتاج حسب الطلبFabrication sur commande (MTO)Siparişe göre üretim (MTO)Production starts only after a specific buyer has confirmed a specific order, with quantity, price and delivery date agreed.
13Next

Lesson 13.3.3: Adding lead time and safety stock to a material requirement plan

You now know how to combine two orders' requirements for the same fabric into one figure. The next lesson looks at Rowad Knits, the mill supplying that fabric, and how it adds lead time and safety stock on top of a combined material requirement before it can promise delivery. Back to the course map

14Ladder

RecognizeTell two orders sharing the same or a similar fabric apart from two orders using unrelated fabrics.
ConnectSee how each order's own requirement is calculated first, then added into one combined figure.
CompareTell a combined purchase order's efficiency against sending two separate, smaller purchase orders.
DecideConfirm two fabrics are close enough before combining their requirements into one purchase order.