A merchandiser follows an order until the tracker's last row is marked Done. This lesson is about that last row. Once the cartons leave the factory, it feels finished: the goods are gone, the ship has sailed, everyone moves on to the next order. But loading the goods is not the same as closing the order. A final inspection must pass, a set of shipping documents must match the purchase order exactly, and the buyer must confirm the goods arrived and are accepted, before the order is truly done.
Without this check, a factory can ship a good order and still lose money weeks later. A mismatched invoice can make a bank refuse payment. A missed inspection can mean the buyer finds a fault the factory never caught. Marking "Done" too early hides a problem instead of closing it. This lesson teaches the mainly-money flow that closes an order: which checks come after shipment, what documents must match, and how closing an export order compares with closing a domestic one, using Cedar & Co. as the domestic case.
You need: no earlier lesson is required, though lesson 5.4 on production checkpoints and lesson 1.4 on AQL inspection give useful background.
By the end of this lesson you can:
Not covered here: how the AQL sample size and pass/fail rule work (lesson 1.4), how a letter of credit and FOB terms are agreed in the first place (lesson 1.2), and how production is tracked day to day before shipment (lesson 5.4).
| Term | Meaning |
|---|---|
| Final inspection | The last check of the finished, packed goods, done just before loading; a fail can stop shipment at the last moment. |
| Packing list | States how the goods are packed: pieces per carton, and total cartons. |
| Commercial invoice | States the price and value of the goods shipped; used by customs and the bank. |
| Bill of lading | The shipping line's proof of loading; its date is the FOB hand-over record. |
| FOB (free on board) | The factory delivers on board the ship at its own port; ownership passes there. |
| Letter of credit | A bank promise to pay once shipping documents match the order exactly. |
| Open account | The buyer pays an agreed number of days after delivery, with no bank guarantee. |
| Claim window | The agreed days after delivery in which a buyer may raise a fault before acceptance. |
| Order closure | The point every closing check has passed and the tracker can be marked Done. |
Shipping an order and closing an order are two different events. Shipping means the goods have left the factory. Closing means three separate checks have all passed: the final inspection of the finished, packed goods; a matching set of shipping documents; and the buyer's acceptance of what arrived, or a clear dispute raised within the agreed window. Only when all three are confirmed can the order's final tracker row be marked Done. A shipped order with an unchecked document or an unconfirmed delivery is still open, even though the ship has already sailed.
Every order closes against the same three checks, but what satisfies each check differs by order shape, market and business model. A new merchandiser who has only closed one kind of order will misread the next one.
| What can differ | The shapes you will meet | Why it matters |
|---|---|---|
| The shipping documents | Export orders need a packing list, commercial invoice and bill of lading that all state the same quantity and price. A domestic order instead uses a delivery note matched against the purchase order; there is no bill of lading because the goods never board a ship. | A missing or mismatched export document can stop a bank payment; a missing domestic delivery note leaves no proof the shop received the goods. |
| The hand-over point | Export FOB orders hand over ownership and risk at loading, recorded by the bill of lading's date. Domestic orders hand over at local delivery, recorded by a signed delivery note at the buyer's own shop or warehouse. | The hand-over point decides the moment risk passes; without it recorded, a loss in transit has no clear owner. |
| How payment is reconciled at closing | Under a letter of credit, the bank checks the documents against the order before it pays; a mismatch anywhere can delay the whole payment. Under open account or a domestic 60-day term, there is no bank document check; the factory or brand simply invoices and waits for the agreed payment date. | A letter of credit turns a small paperwork error into a payment delay; an open account order has no such bank gate, so its risk is late payment, not blocked payment. |
| The claim window | Export buyers often have a set number of days after arrival to raise a claim. Domestic retail chains with their own shops, like Cedar & Co., can confirm receipt the same day the goods reach a shop, since there is no ocean transit to wait out. | A shorter domestic claim window closes the order faster, but only once every shop that received goods has actually confirmed them. |
| The inspection standard | A basic cotton T-shirt order uses AQL sampling on the finished, packed cartons. For home textiles and towels, the buyer's own quality manual sometimes replaces the standard AQL table. | The inspection method can change, but the rule does not: a failed or unchecked final inspection blocks closing on any product. |
Delta Garments finishes Order A, 15,000 basic cotton T-shirts for Northline Apparel. Before the cartons are loaded, a final inspection samples the finished, packed goods and passes. Mona then prepares the packing list, the commercial invoice and the bill of lading so that all three state the same figures: 15,000 pieces at USD 3.20 FOB, matching the purchase order exactly. The cartons are loaded onto Bluewater Line's ship, and the bill of lading's date is the FOB hand-over point: from that date, ownership and risk in the goods belong to Northline Apparel, not Delta Garments. Northline Apparel's own warehouse later confirms it has received all 15,000 pieces. Only at that confirmation does Karim's team mark the tracker's final "Warehouse and distribution" row Done.
Cedar & Co. closes its own domestic orders very differently, and the contrast is worth following closely, because it is easy to assume every order closes the way Order A does. Cedar & Co. is a local brand with 12 shops, buying Make to Stock from its own forecast on a 60-day open account with Delta Garments. A Cedar & Co. order never has an FOB hand-over point or a bill of lading, because the goods never leave the country by sea; a local delivery vehicle carries them from the factory directly to Cedar & Co.'s own shops or central warehouse. There is no letter of credit to reconcile documents against either, since a bank is not involved in the payment: Cedar & Co. simply owes Delta Garments the invoice amount 60 days after delivery. Closing a Cedar & Co. order therefore means two things, not three: confirming that Cedar & Co.'s own shops actually received the goods, matched against the delivery note and the purchase order, and recording that payment is due in 60 days. There is no bank to satisfy and no sea transit to wait out, so a domestic order can often close within days of delivery, while an export order under a letter of credit cannot close until the bank itself has checked the documents.
Order A's value is fixed by its own figures: 15,000 pieces at USD 3.20 FOB. Every shipping document must repeat this same total exactly, because the bank pays against the documents, not against the goods themselves.
The packing list, the commercial invoice and the bill of lading must each show 15,000 pieces and USD 48,000. If any one of the three states a different quantity or price, even by one piece or one cent, the bank can refuse to release the USD 48,000 until the documents are corrected, whether or not the goods have already left the port.
The methodA common mistake is to close the tracker the moment the goods leave the building, whether that is loading day on an export order or delivery day on a domestic one. Loading is the FOB legal hand-over point, and local delivery is the domestic equivalent, but neither one is the same as the order being administratively closed. A shipped order with a document mismatch, or a delivered order the shop has not yet confirmed, can still turn into a payment delay or a dispute weeks later, long after everyone assumed the order was finished.
Shipping an order and closing it are not the same thing. Closing needs three things: the finished goods pass a last inspection, the shipping documents all say the same quantity and price, and the buyer confirms the goods arrived and are accepted. For an export order, that means a packing list, invoice and bill of lading matching a letter of credit's terms. For a domestic order, like Cedar & Co.'s, there is no ship and no bank: a delivery note is matched instead, and payment is simply due after an agreed number of days. Only once every check has passed should the tracker's last row be marked Done, not just "shipped" or "delivered".
Order A's goods are loaded on the ship on 2026-04-13, exactly on the planned shipping date shown on the tracker. Karim asks Mona to mark the order "Done" that same day, since the cartons have left the factory on time.
The tracker's working template records this stage as follows:
Is loading day the right moment to mark Order A's final tracker row Done? Decide before opening the answer.
Not yet. Two facts decide this together.
First, the hand-over point. Loading on 2026-04-13 is the FOB legal hand-over: ownership and risk have passed to Northline Apparel. But that is a transfer of ownership, not a statement that the order is closed.
Second, the documents and acceptance. The commercial invoice, packing list and bill of lading still need to be confirmed as matching 15,000 pieces at USD 3.20 exactly, and Northline Apparel still needs to confirm receipt or let the claim window pass with no dispute. Neither has happened yet on loading day.
Marking the tracker Done on 2026-04-13 would hide a real risk: a document mismatch that is not caught until the bank reviews it could delay the USD 48,000 payment for weeks, long after Mona has stopped watching this order.
Using Order A's own figures, the cost of skipping the document check is not a new fee; it is the whole order's payment, delayed.
If the commercial invoice or bill of lading states even a slightly different quantity or price than the purchase order and the letter of credit expect, the bank can refuse to release any of that USD 48,000 until Delta Garments corrects the documents. That is the entire order's value at risk over a paperwork error, not a shipping error. Cedar & Co.'s domestic orders carry a different, smaller risk at this stage: with no bank document check, a mismatch there mainly risks a slower confirmation from the receiving shop, not a blocked payment, because the 60-day open-account payment is not conditional on document matching the way a letter of credit is.
Open the Log sheet. Find the "Warehouse and distribution" row, the final stage. Do not change its status on the day the goods are loaded or delivered.
| Column | What to check before marking Done |
|---|---|
| Actual date | Fill in only once inspection, documents and acceptance are confirmed, not on the loading date alone. |
| Status | Set to "Done" only after step 4 of the method; otherwise leave it "On track". |
| Notes | Record the last check to finish, for example "documents matching" or "shop confirmed". |
For Order A, that means the bill of lading, documents and Northline Apparel's receipt are confirmed. For Cedar & Co., it means the delivery note and shop's receipt are confirmed; the columns stay the same.
1. Order A's goods are loaded on the ship on the planned shipping date. Is that the moment to mark the tracker's final row Done?
2. Name the three shipping documents that must state the same quantity and price as an export purchase order.
3. A different export order for 8,000 pieces at USD 4.50 FOB ships with a commercial invoice stating USD 35,000. What should happen next?
| EN | AR | FR | TR | Meaning |
|---|---|---|---|---|
| Final inspection | الفحص النهائي | Inspection finale | Nihai kontrol | The last check of the finished, packed goods, done just before or at loading; a fail can stop shipment even at the last moment. |
| Packing list | قائمة التعبئة | Liste de colisage | Çeki listesi | The document that states how the goods are packed: how many pieces are in each carton, and how many cartons in total. |
| Commercial invoice | الفاتورة التجارية | Facture commerciale | Ticari fatura | The document that states the price and value of the goods being shipped, used by customs and by the bank. |
| Bill of lading | بوليصة الشحن | Connaissement | Konşimento | The shipping line's document proving the goods were loaded; its date is the legal record of the FOB hand-over. |
| FOB (free on board) | تسليم على ظهر السفينة في ميناء المصنع | FOB (franco à bord) | FOB (gemide teslim) | The factory delivers the goods on board the ship at its own port. Freight from there is the buyer's cost. |
| Letter of credit | اعتماد مستندي | Lettre de crédit | Akreditif | A bank promise to pay the factory once the shipping documents match the order. |
| Open account | حساب مفتوح | Compte ouvert | Açık hesap | A payment method where the buyer pays the factory an agreed number of days after delivery, with no bank guarantee in between. |
| Claim window | مهلة الشكوى | Délai de réclamation | Şikayet süresi | The agreed number of days after delivery in which a buyer may raise a fault or shortage before the order counts as accepted. |
| Order closure | إغلاق الطلبية | Clôture de la commande | Sipariş kapanışı | The point at which every closing check has passed and the tracker's final stage can be marked Done, not merely "shipped". |
You now know how one order runs from confirmation to a closed tracker row. The next course steps back to look at many orders at once: how a brand plans a whole collection, and how that plan turns into the individual purchase orders you have been tracking in this course. Back to the course map