Every apparel order passes through an approvals stage before bulk cutting starts, and every approvals stage produces more than one sample, not one. A merchandiser who hears "the sample is approved" and stops asking which sample can let a factory cut fabric it should not yet touch. This lesson mainly teaches the decision flow: which sample approval, specifically, tells you that bulk production may begin, and which approvals tell you something else entirely, useful but different. Without this, a factory can spend a full order's cutting cost on the strength of an approval that never actually checked the thing that later went wrong.
You need: the six stages of Order A's timeline from lesson 5.1, including the 2-week approvals stage, and the size-M measurements (body length, half chest, sleeve length and sleeve width) used when a garment's fit is checked.
By the end of this lesson you can:
Not covered here: what a purchase order must contain before the approvals stage can even start (lesson 5.3), and how actual dates and status are logged once production is running (lesson 5.4).
| Term | Meaning |
|---|---|
| Proto sample | The first, rough sample from the tech pack, often in the wrong fabric, proving the design idea works. |
| Fit sample | A sample in the correct fabric at the sample size, checked against the size specification to prove the garment fits. |
| Sales sample | A sample shown to the buyer's customers or sales team, sometimes before the order is confirmed. |
| Pre-production (PP) sample | A sample made from the actual bulk fabric and trims, the last sample checked before bulk cutting begins. |
| Sample size | The one size, usually M, that samples are made in and measured against. |
| Size specification | The body measurements, plus cutting allowance, that a garment in a given size must meet. |
| Bulk fabric | The actual fabric batch bought for the full order quantity, unlike the small quantity used for a sample. |
| Dye lot | One batch of fabric dyed together, which can differ slightly in shade or hand-feel from another batch of the same colour. |
| Turnaround time | The time a buyer takes to review a sample and send back comments or approval. |
| Approvals | The stage where samples are made and signed off by the buyer before bulk production starts. |
A proto sample proves the design idea works at all. A fit sample proves the garment fits to the size specification. A sales or pre-production sample proves the bulk fabric, trims and construction match what was actually approved. Each answers a different question, and approving one of them does not approve the others. Treating "approvals" as a single tick-box hides which specific question has, and has not, been answered.
| What can differ | The shapes you will meet | Why it matters to you |
|---|---|---|
| Proto sample | Made from the tech pack, often in a stand-in fabric close to the real one, sometimes skipped on a simple repeat style the factory has made before. | It only checks the construction idea; a buyer who signs off a proto sample has not yet seen the real fabric or the real fit. |
| Fit sample | Made in the correct fabric at the sample size, usually M, and measured against the size specification; commonly needs a second "fit 2" round if the first fails. | It proves the garment fits one size on one body of measurements, not that the bulk fabric batch is acceptable. |
| Sales sample | Shown to the buyer's own customers, sales agents, or an internal buying meeting, sometimes before the order is even fully confirmed. | Its approval is a commercial decision to go ahead with the style at all; it does not check construction or the bulk fabric either. |
| Pre-production (PP) sample | Made from the actual bulk fabric and trims once the bulk fabric has arrived; this is what should trigger bulk cutting. | It is the only sample that checks the real dye lot, hand-feel and trims the factory will actually cut, not a stand-in. |
None of these rounds replaces another. A style with a strong sales sample and a passed fit sample can still fail at PP sample stage if the bulk dye lot comes back a shade off, and that failure has nothing to do with either earlier approval.
The case we followBefore Delta Garments cuts Order A's 15,000 pieces, Northline Apparel's buyer Sara approves a proto sample, checking the construction of the basic cotton T-shirt. Next, Delta Garments' merchandiser Mona sends a fit sample, made in the correct 180 GSM single jersey at size M, checked against the size specification: body length 72 cm plus 4 cm cutting allowance, half chest 53 cm plus 2 cm, sleeve length 22 cm plus 2 cm, sleeve width 44 cm cut. Sara approves the fit sample. Only after the bulk fabric batch arrives from Colorline Dyeing does Delta Garments cut a pre-production sample from that specific batch and send it to Sara. Only once Sara signs off the PP sample does bulk cutting begin.
| Sample round | Made from | Checked by | What it proved |
|---|---|---|---|
| Proto sample | Tech pack, stand-in fabric | Sara (Northline Apparel) | The construction idea works |
| Fit sample | Correct 180 GSM fabric, size M | Sara, against the size specification | The garment fits size M |
| Pre-production (PP) sample | The actual bulk fabric batch from Colorline Dyeing | Sara | The bulk fabric batch matches what was approved |
Lesson 5.1 gives Order A's approvals stage as 2 weeks inside the 16-week timeline. This lesson shows what fills those 2 weeks: production time for a proto sample, then Sara's turnaround time to review it; production time for a fit sample, then another turnaround; production time for a PP sample, then a final turnaround, all before cutting can start.
A common mistake is to read a fit sample approval as covering the whole approvals stage. A fit sample proves only that the garment fits; it says nothing about whether the actual bulk fabric batch, which can differ slightly in shade, weight or hand-feel from the fit sample's fabric, will still meet the buyer's expectations. Only a PP sample, made from the real bulk fabric, proves that. Cutting bulk fabric on the strength of a fit-sample approval alone risks the full value of the pieces cut before anyone checks whether the bulk batch was actually acceptable.
Before a factory cuts a full order, buyers check several samples, not one. A first rough sample checks whether the design idea works. A second sample, made in the correct fabric and measured carefully, checks whether the garment fits. A sample shown to the buyer's own sales team checks whether people want to buy it. A last sample, made from the real fabric bought for the whole order, checks whether that real fabric is still what everyone agreed on. Approving one of these does not approve the others. Only the last one, made from the real fabric, should ever be the signal to start cutting the whole order.
Karim, the production manager at Delta Garments, tells Mona, the merchandiser, that Order A's fit sample was approved by Sara last week. The bulk fabric has now arrived from Colorline Dyeing, the mill. Karim wants to release it for cutting today.
Is the fit-sample approval enough to start cutting the bulk fabric that has just arrived? Decide before opening the answer.
No. Two facts decide this together.
First, what the fit sample actually proved. The approval record shows Sara approved the fit sample against the size-M specification. That proves construction and fit, nothing more. It says nothing about the bulk fabric that has only just arrived from Colorline Dyeing.
Second, what has not yet happened. No pre-production sample has been made from this specific bulk fabric batch, and none has been sent to Sara for approval. Bulk dye lots can differ slightly in shade or hand-feel from the fabric used for the fit sample, even from the same mill and the same order.
A pre-production sample must be cut from this bulk fabric batch and approved by Sara before bulk cutting starts. If Karim cuts now and the bulk batch turns out to have a shade or hand-feel problem, Delta Garments will have already spent cutting and sewing cost on pieces the buyer may reject.
Order A's cutting-stage value, from lesson 1.2 (the ownership lesson), is USD 2.45 per piece, or USD 36,750 for the full 15,000-piece order. That USD 2.45 is the fabric already bought and the labour already spent making each piece by the cutting stage. Framed qualitatively: the exact loss depends on how many pieces are cut before a fabric problem is found.
Catching a bulk-fabric problem at the PP-sample stage costs only the sample's own small piece of fabric. Skipping that check and finding the same problem after cutting starts risks the full cutting-stage value of the order, USD 36,750, because that fabric and labour have already been spent on pieces that may now need to be re-cut or scrapped.
The Log sheet has one row for "Approvals", with its planned date, actual date, status and notes. That single row hides the proto, fit and PP rounds this lesson covers. "Done" only belongs there once the PP sample specifically has been approved, not an earlier one.
If approvals runs late, use the notes column to name which sample round caused it. This needs no new sheet or column; the existing notes column, read carefully, already covers it.
| Stage | Planned date | Actual date | Status | Notes |
|---|---|---|---|---|
| Approvals | 2026-01-19 | 2026-01-24 | Late | PP sample re-cut, bulk dye lot too dark; proto and fit were on time |
Download the workbook from the course page and use this pattern for your own order's Approvals row.
1. What does a fit sample specifically prove?
2. Which sample should be approved immediately before bulk cutting begins?
3. A different factory is making a 5,000-piece order of woven shirts. The buyer approves a fit sample in week 3, then the factory waits until week 7 for the PP sample to be approved before cutting. Why might this gap between fit-sample approval and PP-sample approval cause a delay an order tracker would flag as late?
| EN | AR | FR | TR | Meaning |
|---|---|---|---|---|
| Proto sample | عينة البروتو | Prototype (échantillon proto) | Proto numune | The first, rough sample made from the tech pack, often in the wrong fabric, to prove the design and construction idea works before investing further. |
| Fit sample | عينة الفيت | Échantillon de fit | Fit numunesi | A sample made in the correct fabric at the sample size, checked against the size specification to prove the garment fits. |
| Sales sample | عينة المبيعات | Échantillon de vente | Satış numunesi | A sample shown to the buyer's own customers or sales team, sometimes before the order is fully confirmed, to gauge interest. |
| Pre-production (PP) sample | عينة ما قبل الإنتاج (PP) | Échantillon de pré-production (PP) | Ön üretim numunesi (PP) | A sample made from the actual bulk fabric and trims, the last sample checked before bulk cutting begins. |
| Sample size | مقاس العينة | Taille échantillon | Numune bedeni | The one size, usually M, that samples are made in and measured against, rather than every size in the order. |
| Size specification | مواصفات المقاس | Spécification de taille | Beden spesifikasyonu | The set of body measurements, plus cutting allowance, that a garment in a given size must meet. |
| Bulk fabric | قماش الإنتاج الفعلي (بلك) | Tissu de production (bulk) | Toplu üretim kumaşı (bulk) | The actual fabric batch bought and dyed for the full order quantity, as opposed to the small quantity used to make a sample. |
| Dye lot | دفعة الصباغة | Lot de teinture | Boya partisi | One batch of fabric dyed together in the same vat, which can differ slightly in shade or hand-feel from another batch of the same colour. |
| Turnaround time | وقت الرد | Délai de retour | Geri dönüş süresi | The time a buyer takes to review a sample and send back its comments or approval. |
| Approvals | الموافقات | Approbations | Onaylar | The stage where samples are made and signed off by the buyer before bulk production starts. |
You now know that "approvals" hides several sample rounds, each proving something different. The next lesson steps back one stage further and asks what a purchase order itself must already contain before a factory should even start the approvals stage. Back to the course map