This page is for a merchandiser, a costing clerk, or a factory owner who has to explain why an order confirmed at a profitable price can still finish with less profit than planned, or with none at all. At work, a factory often treats the price agreed with the buyer as the end of the profitability question. It is only the start. This lesson mainly teaches the money flow: it separates the profit a confirmed price plans for from the profit an order actually earns once every real cost of making it is counted.
Delta Garments confirms Order A with Northline Apparel at FOB USD 3.20 per piece, planning a profit of USD 0.26 per piece, USD 3,900 across 15,000 pieces. That plan is built from five cost components: fabric, trims, making, overhead and profit. Every one of those components can move once production starts. Without this skill, a factory treats a confirmed price as a guaranteed profit and never checks whether the order's actual costs stayed inside the plan that price was built on.
You need: the five cost components of a garment's price from lesson T01-C07-L01 (fabric, trims, making, overhead, profit). You do not need any accounting qualification.
By the end of this lesson you can:
Not covered here: building the order's own full profit and loss statement (lesson T16-C04-L02), spreading overhead across several orders at once (lesson T16-C04-L03), and reading a factory's whole monthly result (lesson T16-C04-L04).
| Term | Meaning |
|---|---|
| Cost component | One part of a garment's total price: fabric, trims, making, overhead, or profit. |
| Planned cost | The cost of each component as built into the price at the time the order was confirmed. |
| Actual cost | The cost of each component as it really turns out once the order is made. |
| Cost variance | The difference between a planned cost and the actual cost for the same component. |
| Overtime cost | The extra cost of paying operators to work beyond normal hours to finish an order on time. |
| Profit margin | The profit component of a price, stated per piece or as a share of the price. |
A confirmed order price is built from five cost components added together: fabric, trims, making, overhead, and profit. The profit component is planned at the moment the price is agreed, based on what fabric, trims, making and overhead are expected to cost. It is not yet earned. An order is only proven profitable once it ships, when every actual cost of the four other components can be compared against what was planned for them. If any actual cost runs above its planned figure, the difference comes straight out of the planned profit, because the buyer's price does not move once it is confirmed. This is why a merchandiser who only checks the confirmed price at the start of an order, and never again until shipment, cannot actually say whether that order made money; the price only ever describes the plan, and the plan is not the same fact as the result.
A merchandiser meets several different shapes of this same gap across a normal season, and learning to recognise each one prevents a confirmed price from being mistaken for a proven profit.
| What can differ | The shapes you will meet | Why it matters |
|---|---|---|
| Export order at a fixed FOB price | Order A is confirmed with Northline Apparel at FOB USD 3.20; the price cannot change once confirmed, whatever the order actually costs to make. | Every extra actual cost is absorbed entirely inside the planned profit; the buyer's price gives no room to pass a cost increase on. |
| Domestic order at a wholesale price | An equivalent-value domestic order for Cedar & Co. is sold at an agreed wholesale price on 60-day open account. | The same fixed-price pressure applies; a domestic buyer's price is just as fixed as an export buyer's once agreed. |
| Making cost running above plan | Delta Garments falls behind schedule on Order A and adds overtime shifts to finish sewing on time. | Overtime raises the making component's actual cost above its planned figure, directly reducing the planned profit. |
| Make to Order versus Make to Stock | Delta Garments only starts Order A once Northline Apparel confirms it; a Make to Stock brand like Cedar & Co. commits to making costs against its own forecast, before any buyer has confirmed a sale. | A Make to Stock order carries an extra risk a Make to Order export order does not: the forecast itself, not only the cost components, can turn out wrong. |
Order A is confirmed at FOB USD 3.20, planning USD 0.26 profit per piece. Partway through the 16-week timeline, Karim, the production manager, reports that sewing is behind schedule. To protect the shipment date at the end of week 16, Delta Garments adds overtime shifts. Overtime is already a fixed, known cost for Order A: USD 0.15 per piece if used across the whole order. Karim now has to work out how much of the planned USD 0.26 profit that decision removes, before deciding whether overtime is still the right choice.
Overtime does not erase Order A's profit. It removes 57.7% of it, leaving USD 1,650 instead of the planned USD 3,900. Karim's decision is still worth taking if the alternative, missing the ship date, costs more.
The methodA common mistake is assuming that once a buyer confirms a price, the planned profit is already earned. The confirmed price only fixes what the buyer pays; it does not fix what the order actually costs to make. A merchandiser who stops checking cost components once an order is confirmed can discover, only at shipment, that overtime, a fabric price change, or a rework cost has quietly removed most of the planned profit. What this costs a factory that gets it wrong is real: a factory that keeps confirming orders without tracking their actual costs against the plan can run a season of orders that all looked profitable on paper and earn far less than its own costing sheets promised. The mistake is rarely a single large loss on one order; it is usually many small, unwatched cost overruns spread across many orders, each one small enough to go unnoticed until the whole season's result is added up and falls short of the plan.
A confirmed order price plans for a profit. It does not prove one. The price is built from five parts: fabric, trims, making, overhead and profit. Once production starts, the first four parts can cost more or less than planned, but the buyer's price stays fixed. Any extra cost comes straight out of the planned profit, because there is nowhere else for it to come from. An order's real profit is only known once it ships and every actual cost is counted. Treating a confirmed price as a guaranteed profit, without checking what the order actually cost to make, is the mistake this lesson warns against.
Order A is in week 11 of its 16-week timeline. Karim reports that sewing is three days behind schedule, which risks missing the port cut-off on day 13 of the shipping stage and the sailing date at the end of week 16. Two options are open: add overtime shifts across the whole order to recover the lost days, or accept the delay and air freight the finished goods instead of shipping by sea.
Here is the note Karim actually wrote:
Which option keeps more of Order A's planned profit, and by how much? Decide before opening the answer.
Overtime. Two figures in Karim's own note decide this together.
First, the cost of each option. Overtime costs USD 0.15 per piece, USD 2,250 across the whole order. Air freight costs USD 1.80 per piece, USD 27,000 across the whole order, twelve times more than overtime.
Second, what each option leaves of the planned profit. Overtime leaves USD 1,650 of the planned USD 3,900 profit (3,900 - 2,250). Air freight alone would cost USD 27,000 against a planned profit of only USD 3,900, turning the whole order into a loss of USD 23,100 (3,900 - 27,000).
Overtime is the far cheaper way to protect the ship date. Air freight should only ever be the last resort once every other way of recovering a schedule, including overtime, has already failed.
Using Order A's own fixed overtime and air freight figures:
Choosing air freight instead of overtime costs USD 24,750 more, over six times the order's entire planned profit of USD 3,900. A scheduling decision made without comparing it against the order's own planned profit can turn a profitable order into a large loss, even though the buyer's price never changed.
Open the course workbook's "Order P&L" sheet. It lists Order A's five cost components as separate rows, with a planned-cost column and an actual-cost column, and calculates the variance and the resulting actual profit with a live formula. Enter overtime, a fabric price change, or any other extra actual cost as an addition to the relevant component's actual-cost cell, and let the sheet recalculate the order's real profit automatically.
[Download the Order and business P&L sheet](../../templates/T16-C04-order-and-business-pl-sheet.xlsx)
1. What does a confirmed order price actually fix?
2. Order A's planned profit is USD 0.26 per piece. If overtime adds USD 0.15 per piece to every piece in the order, what happens to the planned profit?
3. An export order of 8,000 pieces plans USD 0.30 profit per piece. A fabric price rise adds USD 0.20 per piece in actual cost. What is the actual profit per piece?
| EN | AR | FR | TR | Meaning |
|---|---|---|---|---|
| Cost component | عنصر التكلفة | Élément de coût | Maliyet bileşeni | One part of a garment's total price: fabric, trims, making, overhead, or profit. |
| Planned cost | التكلفة المخططة | Coût planifié | Planlanan maliyet | The cost of each component as built into the price at the time the order was confirmed. |
| Actual cost | التكلفة الفعلية | Coût réel | Gerçekleşen maliyet | The cost of each component as it really turns out once the order is made. |
| Cost variance | فرق التكلفة | Écart de coût | Maliyet sapması | The difference between a planned cost and the actual cost for the same component. |
| Overtime cost | تكلفة العمل الإضافي | Coût des heures supplémentaires | Fazla mesai maliyeti | The extra cost of paying operators to work beyond normal hours to finish an order on time. |
| Profit margin | هامش الربح | Marge bénéficiaire | Kâr marjı | The profit component of a price, stated per piece or as a share of the price. |
You now know that a confirmed price is only a planned profit until the order ships. The next lesson turns Order A's own cost components into a full profit and loss statement, line by line. Back to the course map